Sterling SVL-C, SVL-A, SVL-B, SVL-D Maintenance Intervals, Daily Weekly Every 3 months

Page 30

Chapter 5: Maintenance

Preparations

Please observe the maintenance intervals.

Before starting maintenance work, clean the equipment of oil, fuel or lubricants.

Ensure that materials and incidentals required for operation as well as spare parts are disposed of properly and in an environmentally sound manner.

Use only original manufacturer spare parts.

Keep record of all maintenance and repair procedures.

Caution!

Disconnect the equipment from main electrical supply before

 

starting maintenance procedures to ensure that it cannot be

 

switched on unintentionally. Depressurize all compressed air

 

piping of the equipment before starting maintenance work.

5-1 Maintenance Intervals

Daily:

Weekly:

Every 3 months:

Check the filter for obstructions or damage when doing a material change. Check the setting of the pressure regulator.

Empty the water separator.

Check danger signs on the unit for legibility and completeness. Check for worn tubing or loose electrical connections.

Clean the cartridge filter and screen (depending on accumulation of dust). Blow out the filter from the inside using compressed air.

Check the electrical connections for proper functioning. Drain the compressed air filter trap.

Check all electrical and mechanical connections.

Replace filter (depending on accumulation of dust and condition of filter).

Note:The maintenance intervals provided are average values. The maintenance intervals might be adjusted due to your individual process conditions.

Replace/repair components as required.

SVL-A, SVL-B, SVL-C, & SVL-D Self-Contained Material Loaders - Venturi Style 30 of 49

Image 30
Contents Operation and Installation Instructions SVL-A, SVL-B, SVL-C, & SVL-DPage Shipping Information Unpacking and InspectionTable of Contents Technical Data Safety Instructions How to Use This ManualExplanations and Information For Your Safety How to Use This ManualUnit Safety Maintenance ResponsibilityInstallation General InformationOror Installing the Material Receiver Not to scalePage To Digital Dosing Feeder SF-1 FeederInstalling the Control Assembly AssemblyShop Air Connecting the Compressed Air Supply 10 Venturi AssemblyConnecting Material Lines PerformanceSVL-C Two inlet Installation To Install the Ratio OptionElectrical Connection Functional Description Operational SummaryVenturi Assembly Method of FunctioningControl Assembly Control and Regulator UnitSetup Adjusting Compressed Air FlowPreparations Setting the Mixing Ratio of the Components SVL-C Units Electrical Connection Basic Setting of the Filling Level in the Conveyor HopperMounting OperationEmpty adjustment Programming Full adjustment LockingError messages UnlockingSet-up / Operation Maintenance Maintenance IntervalsDaily Weekly Every 3 months Cleaning the Conveying Filter Pertaining to the use of compressed airCleaning the Compressed Air Filter SVL-AAdjusting the Level Probe DisassemblyTroubleshooting Remedy See Test Steps BelowPage Technical Data Dimension Sheet SVL-ASVL-B SVL-C SVL-D Spare Parts Lists SVL-B SVL-C Control Assembly Wand Assembly 10 Take-Off Wand Assembly Quick Start Guide -SVL Self Contained Material Loader Technical Assistance Parts Department