Observe the safety instructions for the connected units.

Maintenance Responsibility

Before beginning maintenance work: Assign a supervisor.

Inform all other responsible operating personnel. Turn off the main power supply.(If required)

Set all compressed air lines on the unit at zero pressure.

Repair work should ONLY be done by qualified personnel.

ALWAYS turn off the main supply for all electrical work to avoid risk of death or injury.

NEVER operate on a unit that is partially disassembled. This can cause serious injuries including amputation and electric shock.

In case of functional disturbances, switch the unit off IMMEDIATELY. Any errors must be eliminated to avoid accidents.

1-4 Unit Safety

The unit may ONLY be used for conveying plastic granules and regrind on injection molding machines.

NEVER change the settings unless you are able to foresee the consequences.

Use ONLY original manufacturer parts.

Follow a regular maintenance schedule.

Keep records of all maintenance and repair work.

Be aware that electronic subassemblies may be damaged by static discharge.

Before initial operation and at regular intervals, check all electrical connections for proper fit.

NEVER modify sensors without knowing their precise functions.

Make sure all plugs are connected properly.

Note the carrying capacity of the machine flange.

Read the operating manuals of the connected units.

SVL-A, SVL-B, SVL-C, & SVL-D Self-Contained Material Loaders - Venturi Style 9 of 49

Image 9
Contents SVL-A, SVL-B, SVL-C, & SVL-D Operation and Installation InstructionsPage Unpacking and Inspection Shipping InformationTable of Contents Technical Data How to Use This Manual Safety InstructionsExplanations and Information How to Use This Manual For Your SafetyMaintenance Responsibility Unit SafetyGeneral Information InstallationOror Not to scale Installing the Material ReceiverPage SF-1 Feeder To Digital Dosing FeederInstalling the Control Assembly AssemblyShop Air 10 Venturi Assembly Connecting the Compressed Air SupplyPerformance Connecting Material LinesTo Install the Ratio Option SVL-C Two inlet InstallationElectrical Connection Operational Summary Functional DescriptionMethod of Functioning Venturi AssemblyControl and Regulator Unit Control AssemblySetup Adjusting Compressed Air FlowPreparations Setting the Mixing Ratio of the Components SVL-C Units Mounting Basic Setting of the Filling Level in the Conveyor HopperElectrical Connection OperationProgramming Empty adjustmentLocking Full adjustmentUnlocking Error messagesSet-up / Operation Maintenance Maintenance IntervalsDaily Weekly Every 3 months Pertaining to the use of compressed air Cleaning the Conveying FilterSVL-A Cleaning the Compressed Air FilterDisassembly Adjusting the Level ProbeRemedy See Test Steps Below TroubleshootingPage Technical Data SVL-A Dimension SheetSVL-B SVL-C SVL-D Spare Parts Lists SVL-B SVL-C Control Assembly Wand Assembly 10 Take-Off Wand Assembly Quick Start Guide -SVL Self Contained Material Loader Parts Department Technical Assistance