Sterling SVL-A, SVL-B, SVL-C, SVL-D Installing the Material Receiver, Not to scale

Page 12

2-2 Installing the Material Receiver

The self contained material loader can be installed directly on the processing machine.

Make sure that all connections are tight so that the conveying performance is not impaired. The material receiver is equipped with a mounting flange.

Depending on the position, drill the holes for fastening the conveyor hopper to the processing machine. One of 2 standard bolt patters may be used, sight glass or bin mounted.(as shown in fig. 2.4)

Mount the material receiver on the processing machine.

Install the vinyl flexible hose on the material receiver inlet and on the venturi assemblies using the hose clamps that are supplied.

Make sure all equipment is properly grounded to minimize static and risk of shock.

Note: The hopper should not touch any other component.

Figure 2.4

(not to scale)

Sight Glass Mounting Flange

Bin Mount Mounting Flange

SVL-A, SVL-B, SVL-C, & SVL-D Self-Contained Material Loaders - Venturi Style 12 of 49

Image 12
Contents Operation and Installation Instructions SVL-A, SVL-B, SVL-C, & SVL-DPage Shipping Information Unpacking and InspectionTable of Contents Technical Data Safety Instructions How to Use This ManualExplanations and Information For Your Safety How to Use This Manual Unit Safety Maintenance ResponsibilityInstallation General InformationOror Installing the Material Receiver Not to scalePage To Digital Dosing Feeder SF-1 FeederInstalling the Control Assembly AssemblyShop Air Connecting the Compressed Air Supply 10 Venturi AssemblyConnecting Material Lines PerformanceSVL-C Two inlet Installation To Install the Ratio OptionElectrical Connection Functional Description Operational SummaryVenturi Assembly Method of FunctioningControl Assembly Control and Regulator UnitSetup Adjusting Compressed Air FlowPreparations Setting the Mixing Ratio of the Components SVL-C Units Basic Setting of the Filling Level in the Conveyor Hopper MountingElectrical Connection OperationEmpty adjustment ProgrammingFull adjustment LockingError messages UnlockingSet-up / Operation Maintenance Maintenance IntervalsDaily Weekly Every 3 months Cleaning the Conveying Filter Pertaining to the use of compressed airCleaning the Compressed Air Filter SVL-AAdjusting the Level Probe DisassemblyTroubleshooting Remedy See Test Steps BelowPage Technical Data Dimension Sheet SVL-ASVL-B SVL-C SVL-D Spare Parts Lists SVL-B SVL-C Control Assembly Wand Assembly 10 Take-Off Wand Assembly Quick Start Guide -SVL Self Contained Material Loader Technical Assistance Parts Department