Eaton Electrical 10640205 Commissioning, AC Installation, Inserting the Access Power Rectifiers

Page 25

Data Power Solutions Quick Start Guide

Desktop Versions – If APS3-06X dc power systems are fitted with three rectifiers, then only two ac power cords may be connected to one building branch circuit. The third ac power cord must be connected to a separate building branch circuit. Failure to do so voids all safety approvals.

Earthing – APS dc power systems are classified as “Class 1” equipment that must be provided with an earth connected to the “Protective Earthing Conductor” in the building wiring. The earth conductor of each ac power cord must be connected to the “Protective Earthing Conductor” in the building wiring.

Earth Leakage Current – The maximum earth leakage current of each Access Power Rectifier is 1.5 mA. Ensure that any upstream Residual Current Devices (RCDs) are appropriately rated.

AC Installation

Install all ac cabling between the ac supply point and the APS dc power system according to the ac supply requirements above, but do NOT switch on the ac supply at this stage.

Commissioning

Inserting the Access Power Rectifiers

Do NOT switch on the ac supply at this stage.

Step 1 – Unpack the rectifiers and inspect them carefully for possible damage that may have occurred in transit. Report any damage immediately, using a completed Equipment Incident Report (located at the back of this guide) to supply all relevant details. Fax the completed form to your local Eaton dc product representative. Keep the original packaging. You will need this if any equipment needs to be returned to your nearest authorized service agent for replacement or repair.

Step 2 – Align the rectifier with the burst-out guides in the shelf.

Step 3 – Push in the rectifier, to avoid injury to your hands, keep your fingers clear. Slowly push in the rectifier, sliding it along the burst-out guides, until it plugs firmly into the backplane connector. Tighten the rectifier retaining screw with a Pozidriv® screwdriver.

Pre-Power-Up Check

Use the checklist below to complete initial checks before progressing further.

All ac and dc cabling is installed, all cabling is neat and correctly insulated

dc battery and load cabling has the correct polarity

All panels are in place and all empty rectifier slots are covered with blanking panels

The ac supply to the APS dc power system is switched OFF

All circuit breakers at the front of the APS dc power system are switched OFF

Batteries (if fitted) are isolated from the APS dc power system

Copyright © 2006-2009 Eaton Corporation. All Rights Reserved.

25

10640205 February 2009

 

Image 25
Contents Data Power Solutions Quick Start Guide Data Power Solutions Quick Start Guide Contents For Further Information and Technical Assistance Worldwide SupportAccess Power Rectifiers APS3 and APS6 Series 48V DC Power SystemsGeneral Description SM45 Supervisory ModuleLow Voltage Disconnect if applicable Pre-InstallationInputs Data Power Solutions Quick Start Guide Wechselspannungs-Eingänge Entrées Alimentation SecteurOutputs Equipment ClassificationIngressi C.A Entradas CARectifiers Batteries if applicableGleichrichter RedresseursRaddrizzatori RectificadoresServicing Location and EnvironmentEntretien Wartung EMC ComplianceManutenzione ReparacionesMounting the APS DC Power System Location and Environment InstallationInspecting the Equipment and Reporting Damage Important Notes for Rack Mounted SystemsWichtige Hinweise für Anlagen mit Schrankmontage Remarques importantes pour les systèmes montés dans un rackDC Load Cable Specifications Connecting the DC Load CablesClearance Requirements Page Strip cable ends Fit load cable clampsFit cable and sleeves Terminate cablesBattery Sizing Installing the External Batteries if applicableBattery Location Arrange sleeves and tighten clamp screwsBattery Fault Protection Batterieschutz Protection en cas de défaut de la batterieBefore You Start Battery Cable SpecificationsPrepare cable clamp Strip cable and fit sleeveRepeat for other battery cables if required Arrange sleeve and clamp the battery cablesTerminate cable Remove knockout and fit coverMounting the Battery Temperature Sensor Connecting the Battery Temperature Sensor CableConnecting the APS DC Power System to the AC Supply AC Supply RequirementsInserting the Access Power Rectifiers AC InstallationPre-Power-Up Check CommissioningConfiguring the APS DC Power System for Operation Applying AC PowerApplying DC Power to the Load Battery Input Circuit Breakers Output Circuit Breaker Field Replacement and RepairUL Listed Mark Desktop variants APS3-060 & APS3-061System Input SpecificationsSystem Output EnvironmentWeight Dimensions H, W, DRectifiers