Eaton Electrical 10640205, APR48 Installing the External Batteries if applicable, Battery Sizing

Page 19

Data Power Solutions Quick Start Guide

Step 5 – Arrange sleeves and tighten clamp screws

Arrange the sleeves so that they are all within 10mm (3/8”) of the terminals.

Tighten all cable clamp screws. Required torque: 1.5 – 2Nm (13.2 – 17.7 lb-in). Tighten the screws of any unused clamps to prevent access to the dc output terminations.

Installing the External Batteries (if applicable)

This section applies to APS3-059, APS3-061 and APS6-059 dc power systems only.

One 48V battery string can be connected to APS3-059 and APS3-061, and up to three 48V battery strings to APS6-059 dc power systems. A 48V battery string consists of either 24 Valve Regulated Lead Acid (VRLA) 2 V cells or four VRLA 12 V monoblocs.

Because of the wide range of battery types and sizes available, we do not supply batteries with the above mentioned power systems and therefore do not cover battery installation in this guide. Always install batteries according to the relevant battery manufacturer’s instructions.

Battery Sizing

Battery manufacturers provide various types of information for sizing batteries such as constant current discharge and constant power discharge data. Your battery supplier will be able to assist you with sizing the battery for your application. Before a battery can be sized, the following information is required.

Required backup time, minimum cell voltage (typically 1.83V/cell), load power & operating temperature

In data applications most loads are constant power for a specified backup time. Therefore, for sizing a battery for the required backup time, constant power discharge data should be used.

Batteries for use in North America must be a UL recognized type, category BAZR2.

Battery Location

Valve Regulated Lead Acid (VRLA) batteries emit very small amounts of hydrogen gas into the surrounding atmosphere under normal float charging conditions. For that reason batteries should never be installed in a sealed enclosure or cabinet. Install the batteries in a well-ventilated location to prevent accumulation of hydrogen gas to flammable or explosive levels.

Building air conditioning and ventilation systems already in place for optimum equipment operation and comfort of personnel usually meet or exceed VRLA battery ventilation requirements. For specific battery ventilation requirements, always refer to the battery manufacturer’s installation instructions. Avoid:

Installing the batteries next to any heating source or under air ducts.

Exposing part of a battery string to direct sunlight.

Any other locations that would cause temperature variations within the batteries.

Copyright © 2006-2009 Eaton Corporation. All Rights Reserved.

19

10640205 February 2009

 

Image 19
Contents Data Power Solutions Quick Start Guide Data Power Solutions Quick Start Guide Contents For Further Information and Technical Assistance Worldwide SupportSM45 Supervisory Module APS3 and APS6 Series 48V DC Power SystemsAccess Power Rectifiers General DescriptionLow Voltage Disconnect if applicable Pre-InstallationInputs Data Power Solutions Quick Start Guide Wechselspannungs-Eingänge Entrées Alimentation SecteurEntradas CA Equipment ClassificationOutputs Ingressi C.ARectifiers Batteries if applicableRectificadores RedresseursGleichrichter RaddrizzatoriServicing Location and EnvironmentEntretien Reparaciones EMC ComplianceWartung ManutenzioneImportant Notes for Rack Mounted Systems InstallationMounting the APS DC Power System Location and Environment Inspecting the Equipment and Reporting DamageWichtige Hinweise für Anlagen mit Schrankmontage Remarques importantes pour les systèmes montés dans un rackDC Load Cable Specifications Connecting the DC Load CablesClearance Requirements Page Terminate cables Fit load cable clampsStrip cable ends Fit cable and sleevesArrange sleeves and tighten clamp screws Installing the External Batteries if applicableBattery Sizing Battery LocationBattery Fault Protection Batterieschutz Protection en cas de défaut de la batterieStrip cable and fit sleeve Battery Cable SpecificationsBefore You Start Prepare cable clampRemove knockout and fit cover Arrange sleeve and clamp the battery cablesRepeat for other battery cables if required Terminate cableAC Supply Requirements Connecting the Battery Temperature Sensor CableMounting the Battery Temperature Sensor Connecting the APS DC Power System to the AC SupplyCommissioning AC InstallationInserting the Access Power Rectifiers Pre-Power-Up CheckConfiguring the APS DC Power System for Operation Applying AC PowerApplying DC Power to the Load Desktop variants APS3-060 & APS3-061 Output Circuit Breaker Field Replacement and RepairBattery Input Circuit Breakers UL Listed MarkEnvironment SpecificationsSystem Input System OutputWeight Dimensions H, W, DRectifiers