Step 3 – Terminate cable

Terminate the positive battery cable at the Battery (+) terminal block.

Terminate the negative battery cable at the Battery (-) terminal block.

Tighten the terminal screws. Required torque: 2.5 - 3 Nm (22.1 – 26.5 lb-in).

Ensure that the polarity at the battery terminal blocks matches the polarity of the external battery. Connecting a reverse polarity battery to an APS dc power system will cause damage to the rectifier modules. Such damage will not be covered by the warranty.

16mm battery cable sleeve.

Battery cable clamp with posts removed.

Step 4 – Arrange sleeve and clamp the battery cables

Arrange the cable sleeve so that it is within 10mm (3/8”) of the terminals.

Tighten the cable clamp screws. Required torque: 1.5 – 2Nm (13.2 – 17.7 lb-in).

Step 5 – Repeat for other battery cables (if required)

Repeat the above procedure to connect up to three battery strings to an APS6-059 power system

Step 6 – Remove knockout and fit cover

Remove the battery cable knockout(s) on the dc output cover:

Battery cable knockout.

Remove any sharp edges, in particular the remaining knock-out webs.

Fit the dc output cover.

Copyright © 2006-2009 Eaton Corporation. All Rights Reserved.

23

10640205 February 2009

 

Image 23
Contents Data Power Solutions Quick Start Guide Data Power Solutions Quick Start Guide Contents For Further Information and Technical Assistance Worldwide SupportSM45 Supervisory Module APS3 and APS6 Series 48V DC Power SystemsAccess Power Rectifiers General DescriptionInputs Pre-InstallationLow Voltage Disconnect if applicable Data Power Solutions Quick Start Guide Wechselspannungs-Eingänge Entrées Alimentation SecteurEntradas CA Equipment ClassificationOutputs Ingressi C.ARectifiers Batteries if applicableRectificadores RedresseursGleichrichter RaddrizzatoriEntretien Location and EnvironmentServicing Reparaciones EMC ComplianceWartung ManutenzioneImportant Notes for Rack Mounted Systems InstallationMounting the APS DC Power System Location and Environment Inspecting the Equipment and Reporting DamageWichtige Hinweise für Anlagen mit Schrankmontage Remarques importantes pour les systèmes montés dans un rackClearance Requirements Connecting the DC Load CablesDC Load Cable Specifications Page Terminate cables Fit load cable clampsStrip cable ends Fit cable and sleevesArrange sleeves and tighten clamp screws Installing the External Batteries if applicableBattery Sizing Battery LocationBattery Fault Protection Batterieschutz Protection en cas de défaut de la batterieStrip cable and fit sleeve Battery Cable SpecificationsBefore You Start Prepare cable clampRemove knockout and fit cover Arrange sleeve and clamp the battery cablesRepeat for other battery cables if required Terminate cableAC Supply Requirements Connecting the Battery Temperature Sensor CableMounting the Battery Temperature Sensor Connecting the APS DC Power System to the AC SupplyCommissioning AC InstallationInserting the Access Power Rectifiers Pre-Power-Up CheckApplying DC Power to the Load Applying AC PowerConfiguring the APS DC Power System for Operation Desktop variants APS3-060 & APS3-061 Output Circuit Breaker Field Replacement and RepairBattery Input Circuit Breakers UL Listed MarkEnvironment SpecificationsSystem Input System OutputRectifiers Dimensions H, W, DWeight