Eaton Electrical Maintenance and Care, RTC-50 Controller Troubleshooting, Level of Repair

Page 8

Instructional Booklet

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 8

Effective: June 2007

Instruction Manual for the Eaton RTC-50

 

 

 

Automatic Transfer Switch Controller

SECTION 5: MAINTENANCE, TROUBLESHOOTING, AND REPLACEMENT

5.1 Maintenance and Care

The RTC-50 is designed to be a self-contained and maintenance- free unit. The printed circuit board is conformally coated at the factory. The RTC-50 is intended for service by factory-trained personnel only.

Step 7: Reconnect the wires to J7 and J8.

Step 8: Reapply power to the transfer switch.

Step 9: Place the generator control selector switch in the “AUTO” position after the controller has been replaced. (The Gen- erator may start but will shut down within 5 minutes.)

Test the system for proper functionality.

5.2 RTC-50 Controller Troubleshooting

The Troubleshooting Guide (Table 3) is intended for service per- sonnel to identify whether a problem being observed is external or internal to the unit. For assistance with this determination, con- tact Eaton Electrical. If a problem is identified to be internal, the unit should be returned to the factory for replacement.

Table 3. Troubleshooting Guide.

SYMPTOM

PROBABLE CAUSE

POSSIBLE SOLUTION(S)

“Util Avail” and “Gen Avail”

Power is deficient or absent.

Verify that power is connected

LEDs are not lit.

 

at J1 – J4 and that it is within

 

 

specifications.

 

RTC-50 is malfunctioning.

Replace the unit.

 

 

 

Utility source or Generator

Voltage is not within setpoint

Verify voltage with multimeter.

source is not available when

values.

Check the programmed setpoint

it should be.

 

values.

5.3 Level of Repair

This manual is written with the assumption that only ATS trouble- shooting will be performed. If the cause of malfunction is traced to an RTC-50, the unit should be replaced with a new unit. The malfunctioning unit should then be returned to Eaton Electrical for factory repairs.

5.4 RTC-50 Replacement

WARNING

HIGH VOLTAGES ARE PRESENT IN AND AROUND TRANSFER SWITCH EQUIPMENT. BEFORE ATTEMPTING TO REPLACE ANY COMPONENT, DISCONNECT THE LINE POWER FROM THE EQUIP- MENT BEING SERVICED BY OPENING AND LOCKING OUT, IF POSSI- BLE, THE NEXT HIGHEST DISCONNECT DEVICE. FAILURE TO FOLLOW THIS PROCEDURE COULD CAUSE SEVERE PERSONAL INJURY AND/OR DEATH.

ALWAYS TURN THE UTILITY POWER OFF AND TURN THE GENERA- TOR CONTROL SELECTOR SWITCH TO THE “OFF” POSITION BEFORE ATTEMPTING TO REPLACE ANY COMPONENTS.

Step 1: Turn the Generator Start select to “OFF” before attempt- ing to replace the RTC-50 controller. Ensure all sources of power are removed.

Step 2: Disconnect the J1, J2, J3, J4, and J6 plugs from the controller

Step 3: Disconnect the wires connected to J7 and J8.

Step 4: Remove the four (4) screws located at the corners of the controller that secure it to the power panel. Remove the controller.

Step 5: Align the new controller with the mounting holes. Secure the new controller board using the existing hardware. Tighten the screws.

Step 6: Connect the J1, J2, J3, J4, and J6 plugs to their original receptacles.

For more information visit: www.eaton.com

IB00405004E-70-8664

Image 8
Contents Eaton RTC-50 Automatic Transfer Switch Controller Preliminary Comments and Safety Precautions IntroductionGeneral Information Product OverviewFunctions/Features GlossaryLED Indicators Input/Output ConnectorsHardware Description GeneralGo To Generator Input Output ConnectionsSpecification Summary RTC-50 Controller Specifications OperationOperating Voltage and Measurements Typical Transfer OperationIntroduction Fixed and Jumper-Selectable SettingsProgramming Maintenance and Care RTC-50 Controller TroubleshootingTroubleshooting Guide RTC-50 ReplacementGenerator is powering the load Appendix a Operational FlowchartUtility is powering the load Instructional Booklet Effective June IB00405004E-70-8664 Effective June Descripción Sección 1 Introducción Precaución AdvertenciaComentarios preliminares y precauciones de seguridad Información GeneralGlosario Sección 2 Descripción DEL Equipo Indicadores con diodos emisores de luz LEDProgramación con los puentes Conectores de entrada/salidaEntrada para ir al generador Conexiones de salidaOperación de transferencia típica Sección 3 OperaciónVoltaje operativo y mediciones Tabla 2. Selecciones fijas y seleccionables con puente Sección 4 ProgramaciónIntroducción Resolución de problemas del controlador RTC-50 Tabla 3. Guía para la resolución de problemasManual de instrucciones para el controlador RTC-50 Mantenimiento y cuidadoEl generador está alimentando a la carga Apéndice a Diagrama OperativoEl servicio está alimentando a la carga Folleto instructivo Folleto instructivo Página Efectivo Junio Sommaire Mise EN Garde Commentaires préliminaires et précautions de sécuritéGénéralités Présentation du matérielGlossaire Fonctions/ParticularitésDescription DU Matériel Voyants DELProgrammation des cavaliers Connecteurs dentrée et de sortieEntrée du transfert vers la génératrice Connexions de sortieOpération type de transfert FonctionnementTension dutilisation et mesures Programmation Tableau 2. Réglages fixes et à choisir avec cavaliersENTRETIEN, Dépannage ET Remplacement Le courant de génératrice alimente la charge Annexe a Ordinogramme DE FonctionnementLe courant secteur alimente la charge Livret dinstructions Livret dinstructions Mode demploi de la commande RTC-50 pour