6Connect the input and ground wires to the terminal block according to Figure 20 and Table 2.
Terminal Position
1 2 3
Figure 20. UPS Input Terminal Block
Table 2. UPS Wiring Specifications
Wire Function | Terminal | UPS Wire Function | Terminal Wire | Tightening Torque | |
Position | Size Rating* | ||||
|
|
| |||
|
|
|
|
| |
Input | 1 | Input Ground |
|
| |
|
|
|
| ||
| 2 | L2/Neutral In | 2.49 Nm (22 lb in) | ||
| |||||
|
|
|
| ||
| 3 | L1 In |
| ||
|
|
| |||
|
|
|
|
|
* Use a minimum:
S10 AWG for equipment grounding wire, 75_C copper wire minimum
S8 AWG for input line and neutral wires, 75_C copper wire minimum
7Replace the terminal block cover.
8Continue to the following section, “UPS Initial Startup.”