American Power Conversion 240-320kW manual External Connection

Page 26

External Connection

This auxiliary contact is also called “Normally Open” (NO), because the auxiliary contact will be open when the main contacts are open

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION MODE

When switching Q003 from “OFF or 0” to “ON or 1”, the auxiliary contact has to open BEFORE the corresponding main contacts are closed. When switching Q003 the opposite way from “ON or 1” to “OFF or 0”, the auxiliary contact has to close with a maximum delay of 0.5 seconds from the time when the corresponding main contacts are opened.

This type of auxiliary contact is called an “early break” contact. (This also means that it will “make late” when activated in the opposite direction)

The auxiliary contact is also called “Normally Closed” (NC), because the auxiliary contact will be closed when the main contacts are open

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION

CAUTION!

All wiring to alarm and signal circuit fields to be rated 300V (minimum).

X005 (output relays)

The battery operation signal is received with a 30-second delay. This function is inactive during battery tests. Common fault relay facility is programmable (standard factory setting: 10 sec.) See APC Silcon User Guide for details.

Maximum nominal voltage on contact circuits is 277VAC. If two different phases are involved, maximum phase to neutral voltage should be below 160VAC. Please note that phase L1 is already present on the System Integration Interface board, supplied from the Service Bypass Panel. Therefore, if a phase is needed for alarm or signal purposes, Phase L1 should be used”.

Terminals X001, X003, X005, X004, X012:

Cable size AWG18 to AWG14, use solid copper conductors only.

990-4049

26

Installation Guide APC Silcon 240-320kW 480V UPS

Image 26
Contents APC Silcon 240-320kW 480V UPS Installation Guide Copyright 2001 APC Denmark ApSThank You Installation Guide APC Silcon 240-320kW 480V UPSSafety Symbols used in this manual Contents Installation Guide APC Silcon 240-320kW 480V UPS Tools and Equipment IntroductionIntroduction ToolsUnpacking/Identification of Equipment Unpacking/Identification of EquipmentBattery Cabinet Service Bypass PanelBattery Breaker Box Main UPS systemNema 12 Cover Isolation TransformerSeismic Anchoring Remote DisplayDimensions and Weight InstallationInstallation Requirements on SiteFootprints UPS Cabinet FootprintsConduit Entrance Plate in bottom of the system COM COM FrontTop Cable Entry External Connection Connecting the UPSExternal Connection Connecting AC and DC Power Cables Dual Utility Connection Dual Utility Connection Seperation of AC from DC1 and DC2 Top or Bottom Cable Entry Dual and Single Utility Supply Working Principle of Dual Utility 2 utility supplies Working Principle of Single Utility 1 utility supplySwitching from Dual to Single Utility Input Wiring Stud size M10 M12 Terminals Input Battery Output System earth TypeStud size Terminal Ground terminals System Integration Interface Single Utility Dual UtilityConnecting the System Integration Interface Board SII-board SII BoardExternal Connection External Connection External Connection Parallel Board Parallel BoardPower Cables External Control CablesRelays Relay Number Message Alarm Trigging EventsRelay Board Relay Board FunctionsExternal Connection Cable Sizes Connections Communication Interface / Smart SlotSmartSlot for APC Silcon 240-320kW UPS Priority of APC accessories SmartSlot AccessoriesMultiple SmartSlot Installation introduction Installing accessories procedureInstallation in APC Silcon 240kW and 320kW APC Silcon Battery Cabinets Important Safety InstructionsInstallation of Batteries APC SilconBattery Breaker Box Rear of enclosure Mounting and Connection of Battery Breaker BoxInterconnection See measurementsUPS Installations in Computer Rooms UPS with External Battery via Battery Breaker BoxEPO Principle S002 Choose either Emergency shutdown connection betweenPrinciple diagram UPSSupply Emergency Power Off EPO for UPSUtility Possible UPS operation Tripping Single configuration for Single Utility Utility Possible UPS operation modes Tripping SupplyProgramming Parameter Setting CommentsProgramming ParametersProgramming Example Switch to Bypass Operation Programming KeysProgramming 346V System Configuration438V 326VSeparate Programming Example Change Boost Charge Voltage toProgramming Programming Example Description of SettingsProgramming Parameters for Advanced Parallel Operation Battery Monitor Principle diagram Service Bypass Panel for single operation Options/AccessoriesOptions/Accessories Battery Breaker Box APC Silcon UPS System Integration Interface Mounting and Connecting Service Bypass Panel Options/Accessories Options/Accessories Mounting and Connecting Seismic Anchoring Mounting Seismic Anchoring Nema 12 Cover IP31 Mounting Nema 12 CoverStandard Short-haul RS232 Modem Async Remote DisplayExtension of Remote Display Communication Distance Connections With Converter Connections Without ConverterHost DTE Remote Display DTE Pin Connections for cable from host to ME800A-R2 HostRemote Display Power Supply Screws DP9-FRemote Display Cables Communication FaultRemote Display Setting Remote Display UseIsolation Transformer Module External Temperature Alarm Cable Cabinets and DimensionsConnecting Isolation Transformer FootprintsIsolation Transformer Diagram Delta WYE configuration Dyn11 Isolation Transformer Grounding 6.5.7.1 System GroundingSingle Utility and Redundant System Dual Utility and Single System Dual Utility and Redundant SystemIntersystem Synchronization Unit ISU Intersystem Synchronization UnitIntersystem Synchronization Unit System ISU System Technical Data System SpecificationsSystem Specifications Voltage 3x480VAppendix Installation Planning DataAppendix Fepw TBS,SA RH,RHW Correction Factors APC Silcon Series Limited Factory Warranty WarrantyWarranty APC Corporate How to Contact APCHow to Contact APC APC Denmark