American Power Conversion 240-320kW manual Battery Monitor

Page 53

Programming

If APM should not be tested, “APM test mode active” must be “NO”.

If a system is isolated due to service the station numbers must be reprogrammed for the remaining active systems starting with number 1 and ending with maximum number of active systems. No numbers must be left in this sequence. Furthermore, “Highest station address” must be changed to number of active UPS’s in parallel.

5.4Battery Monitor

Installation of new batteries:

To avoid false alarms, the above procedure MUST be followed.

NOTICE!

Contact your local dealer if you have any questions regarding changing parameters.

990-4049

Installation Guide APC Silcon 240-320kW 480V UPS

53

Image 53
Contents Copyright 2001 APC Denmark ApS APC Silcon 240-320kW 480V UPS Installation GuideThank You Installation Guide APC Silcon 240-320kW 480V UPSSafety Symbols used in this manual Contents Installation Guide APC Silcon 240-320kW 480V UPS Introduction IntroductionTools and Equipment ToolsUnpacking/Identification of Equipment Unpacking/Identification of EquipmentBattery Breaker Box Service Bypass PanelBattery Cabinet Main UPS systemSeismic Anchoring Isolation TransformerNema 12 Cover Remote DisplayInstallation InstallationDimensions and Weight Requirements on SiteUPS Cabinet Footprints FootprintsCOM COM Front Conduit Entrance Plate in bottom of the systemTop Cable Entry External Connection Connecting the UPSExternal Connection Connecting AC and DC Power Cables Dual Utility Connection Dual Utility Connection Seperation of AC from DC1 and DC2 Top or Bottom Cable Entry Dual and Single Utility Supply Working Principle of Single Utility 1 utility supply Working Principle of Dual Utility 2 utility suppliesSwitching from Dual to Single Utility Input Wiring Stud size M10 M12 Terminals Input Battery Output System earth TypeStud size Terminal Ground terminals Single Utility Dual Utility System Integration InterfaceSII Board Connecting the System Integration Interface Board SII-boardExternal Connection External Connection External Connection Parallel Board Parallel BoardExternal Control Cables Power CablesRelay Board Relay Number Message Alarm Trigging EventsRelays Relay Board FunctionsExternal Connection Cable Sizes Connections Communication Interface / Smart SlotSmartSlot for APC Silcon 240-320kW UPS Multiple SmartSlot Installation introduction SmartSlot AccessoriesPriority of APC accessories Installing accessories procedureInstallation in APC Silcon 240kW and 320kW Important Safety Instructions APC Silcon Battery CabinetsAPC Silcon Installation of BatteriesBattery Breaker Box Interconnection Mounting and Connection of Battery Breaker BoxRear of enclosure See measurementsUPS with External Battery via Battery Breaker Box UPS Installations in Computer RoomsS002 Choose either Emergency shutdown connection between EPO PrincipleUPS Principle diagramSupply Emergency Power Off EPO for UPSUtility Possible UPS operation Tripping Utility Possible UPS operation modes Tripping Supply Single configuration for Single UtilityProgramming Parameter Setting CommentsProgramming ParametersProgramming Keys Programming Example Switch to Bypass OperationProgramming 438V System Configuration346V 326VProgramming Example Change Boost Charge Voltage to SeparateProgramming Programming Example Description of SettingsProgramming Parameters for Advanced Parallel Operation Battery Monitor Principle diagram Service Bypass Panel for single operation Options/AccessoriesOptions/Accessories Battery Breaker Box APC Silcon UPS System Integration Interface Mounting and Connecting Service Bypass Panel Options/Accessories Options/Accessories Mounting and Connecting Seismic Anchoring Mounting Seismic Anchoring Mounting Nema 12 Cover Nema 12 Cover IP31Standard Short-haul RS232 Modem Async Remote DisplayExtension of Remote Display Communication Distance Host DTE Remote Display DTE Connections Without ConverterConnections With Converter Pin Connections for cable from host to ME800A-R2 HostScrews DP9-F Remote Display Power SupplyRemote Display Setting Communication FaultRemote Display Cables Remote Display UseIsolation Transformer Module Connecting Isolation Transformer Cabinets and DimensionsExternal Temperature Alarm Cable FootprintsIsolation Transformer Grounding 6.5.7.1 System Grounding Isolation Transformer Diagram Delta WYE configuration Dyn11Single Utility and Redundant System Dual Utility and Redundant System Dual Utility and Single SystemIntersystem Synchronization Unit ISU Intersystem Synchronization UnitIntersystem Synchronization Unit System ISU System System Specifications System SpecificationsTechnical Data Voltage 3x480VAppendix Installation Planning DataAppendix Fepw TBS,SA RH,RHW Correction Factors APC Silcon Series Limited Factory Warranty WarrantyWarranty How to Contact APC How to Contact APCAPC Corporate APC Denmark