Schneider Electric EM4000 manual Receiving, Pre-Installation Checklist, Site Planning

Page 14

PowerLogicTM Series EM4000

930-134-01-A.00

Installation Guide

11/2013

 

 

Installation

This section contains the following installation topics:

“Pre-Installation” on page 6

“Installation Procedures” on page 7

“Connecting Pulse Inputs” on page 26

Pre-Installation

The pre-installation checklist and site planning must be performed before installing the equipment at the site.

Receiving

The equipment required for each PowerLogic EM4000 meter installation includes:

high-density meter (PowerLogic EM4033 or PowerLogic EM4080)

For the PowerLogic EM4033 and PowerLogic EM4080, one 12-ft (4-m) AMP cable with one 50-pin connector supplied with each unit

CD and meter configuration software, this installation manual and an installation record form

When you receive your order, verify that the items listed above are included with the shipment, and visually inspect them for damage. If any parts are missing or damaged, contact your Schneider Electric representative.

Pre-Installation Checklist

The installer must provide the following information, tools, and equipment before proceeding with the installation:

certified current transformers for metering (not supplied)

an appropriate 15-Amp maximum circuit breaker or a fused disconnect switch for the type of panel

current/voltage meter to test the phasing of panels

RJ45 Ethernet patch cable

4-wire 14 AWG (1.63 mm2) cable for three-phase wye connected circuits, or 3-wire 14 AWG (1.63 mm2) cable for a single-phase wye connected circuits

small flat-head screwdriver

#2 Phillips screwdriver

crimping tool

18 AWG butt splice connector

wire strippers

four 1-inch (25 mm) #8 mounting screws suitable for selected mounting surface

Site Planning

1.Determine the number of PowerLogic EM4000 series meters to be installed and ensure adequate space. For clearances, see Figure 3 on page 8.

2.Determine the number of Ethernet drops required, and ensure they are installed before installing the PowerLogic EM4033 and EM4080 meters.

6

©2013 Schneider Electric All Rights Reserved

Image 14
Contents PowerLogicTM Series EM4000 Page Important Information Please noteFCC Part 15 Notice FCC Part 68 NoticeNetwork Compatibility Notice for the Internal Modem Page Table of Contents Schneider Electric All Rights Reserved System Description PowerLogic EM4000 series System SpecificationsIntroduction PowerLogic EM4000 series meter specifications PowerLogic EM4080 front panel Front Panel DisplayPowerLogic EM4033 and PowerLogic EM4080 internal view Safety Precautions Electrical Standards CompliancePre-Installation Checklist InstallationPre-Installation ReceivingMounting the PowerLogic EM4000 meter Installation ProceduresAccess to Power and Lighting 11.0 27.9 cm EM4033 11/2013 Installation Guide Shorting block detail 930-134-01-A.00 Hazard of Electric SHOCK, EXPLOSION, or ARC Flash For a single-phase panel with the 120V variant of the meter Schneider Electric All Rights Reserved From Panel Schneider Electric All Rights Reserved Delta service metering PowerLogic EM4000 meter three-phase Delta service connectionInstalling the Current Transformers PowerLogic EM4033 split-core 0.333V current transformer Source Installing 5A Converters and CTs on the PowerLogic EM4080 Steps Shows a 5A CT connected to the converterPowerLogic EM4080 5A CT connection to converter PowerLogic EM4000 meter CT color pair identification Connecting the Modbus RTU Communications Connecting the CommunicationsConnecting the Ethernet Cable Start-Up Sequence Connecting Pulse InputsManually Testing Communications Display Navigation Normal ModeDiagnostics Mode Recording the Meter Map Installation Record sample shown Maintenance Fuse ReplacementEquipment servicing and access Regulatory ComplianceGraphical symbols that appear on equipment Index NumericsPowerLogicTM EM4000 Series 930-134-01-A.00 Index 11/2013 Page Schneider Electric