Schneider Electric EM4000 manual Maintenance, Fuse Replacement

Page 38

PowerLogicTM Series EM4000

930-134-01-A.00

Installation Guide

11/2013

 

 

Maintenance

Do not perform any operation or maintenance procedures that are not described in this product documentation. Visually inspect the equipment yearly and ensure it is free of dust or other particles. If necessary, wipe with a clean cloth. Individual components are not user-serviceable and must be returned to Schneider Electric for repair.

Fuse Replacement

HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH

Apply appropriate personal protective equipment (PPE) and follow safe electrical work practices. See NFPA 70E.

Turn off all power supplying this equipment before working on or inside equipment.

Always use a properly rated voltage sensing device to confirm the power is off.

Replace all devices, doors and covers before turning on power to this equipment.

Failure to follow these instructions will result in death or serious injury.

1.Turn off all sources of power before attempting to replace the fuse. Always use a properly rated voltage sensing device to confirm the power is off.

2.Remove the outer cover from the unit.

3.Locate fuse F1 at the top left corner inside the unit.

4.Remove the fuse cover, then remove the fuse from the holder as shown in Figure 15.

5.Replace fuse F1 with a fuse that meets the specifications listed in Table 1 on page 2.

6.Replace the fuse cover.

7.Re-install the cover and turn on the power source.

Figure 15: Replacing the fuse

3

 

 

2

Legend:

1

Fuse holder

 

 

2

Fuse

1

3

Fuse cover

30

©2013 Schneider Electric All Rights Reserved

Image 38
Contents PowerLogicTM Series EM4000 Page Important Information Please noteFCC Part 15 Notice FCC Part 68 NoticeNetwork Compatibility Notice for the Internal Modem Page Table of Contents Schneider Electric All Rights Reserved System Description PowerLogic EM4000 series System SpecificationsIntroduction PowerLogic EM4000 series meter specifications PowerLogic EM4080 front panel Front Panel DisplayPowerLogic EM4033 and PowerLogic EM4080 internal view Safety Precautions Electrical Standards CompliancePre-Installation Checklist InstallationPre-Installation ReceivingMounting the PowerLogic EM4000 meter Installation ProceduresAccess to Power and Lighting 11.0 27.9 cm EM4033 11/2013 Installation Guide Shorting block detail 930-134-01-A.00 Hazard of Electric SHOCK, EXPLOSION, or ARC Flash For a single-phase panel with the 120V variant of the meter Schneider Electric All Rights Reserved From Panel Schneider Electric All Rights Reserved Delta service metering PowerLogic EM4000 meter three-phase Delta service connectionInstalling the Current Transformers PowerLogic EM4033 split-core 0.333V current transformer Source Installing 5A Converters and CTs on the PowerLogic EM4080 Steps Shows a 5A CT connected to the converterPowerLogic EM4080 5A CT connection to converter PowerLogic EM4000 meter CT color pair identification Connecting the Modbus RTU Communications Connecting the CommunicationsConnecting the Ethernet Cable Start-Up Sequence Connecting Pulse InputsManually Testing Communications Display Navigation Normal ModeDiagnostics Mode Recording the Meter Map Installation Record sample shown Maintenance Fuse ReplacementEquipment servicing and access Regulatory ComplianceGraphical symbols that appear on equipment Index NumericsPowerLogicTM EM4000 Series 930-134-01-A.00 Index 11/2013 Page Schneider Electric