Furuno DS-60 installation manual Transducer, Installation location

Page 12

1. INSTALLATION

1.4Transducer

The performance of this equipment is directly dependent on the installation of the transducer.

The installation of the transducer and the tank must be accomplished by a dockyard referring to the installation drawings at the later part of this manual.

1.4.1Installation location

To decide the location of the transducer, the following points must be taken into account.

• Locate the transducer of DS-60 at least 2.5 m from the transducer of an echo sounder.

DOPPLER SONAR TRANSDUCER

STERN

BOW

2500 mm or more

Recommended location

for echo sounder transducer

ECHO SOUNDER TRANSDUCER

Separate as far as possible from air bubble sources; e.g., side thruster and water disposal pipes.

Install in close proximity to the keel, for uniform water flow.

Generally, best performance is obtained by mounting on the bow; the stern side is influenced more easily by air bubbles and propeller cavitation.

Do not apply any paint to the transducer face.

1-6

Image 12
Contents Installation Manual Iii00017233810 Safety Instructions System Configurations Equipment Lists Standard supplyOptional Supply Display Unit DS-600 Mounting considerationFlush mount Hanger assembly Type OP26-8, Code No Desktop or table underside mountHow to set the cosmetic cap and alarm lid assy Installation considerations Transceiver Unit DS-620Distributor Unit DS-610 Installation location TransducerInstallation using the transducer tank DS-660 Transducer tank DS-660, sectional viewHex. bolt 15 Seal washer Fixing plate Hex. bolt M6x20 Spring washer M6 Cable assy Metal fixing Transducer tank, sectional view Installation with gate valve DS-661 DS-661 gate valve, sectional viewInstallation Installation Installation How to open the gate valve Junction Box DS-640 option Mounting procedure Mounting considerationsApply silicon rubber to M10 bolts as shown below Pass the cable through the cable gland as shown below Remote Controller RD-501/Dimmer Controller RD-502 option How to change orientation of the front cover of DS-605Leveling adjustment Rate-of-Turn Gyro DS-340 optionThis page is intentionally left blank Wiring Precautions for cable installationConnection of Wago connector Top cover Cable clamps, entrancesTB3 TB1 TB5 TB2 TB4 TB8 DS-610 Distributor Unit DS-620 Transceiver unit DS-600 Display unit DS-600, example of connection Junction Box DS-640, option DS-640 Junction BoxMenu Settings How to Use the Service MenuMenu item Meaning Option How to Set the System Menu How to show the System menuHow to set ship’s data How to enter offset values Meaning Setting rangeHow to correct the ship’s speed This page is intentionally left blank AP-1 Milepost runCalculation with transit posts AP-2 Calculation with DS-60AP-3 Appendix 2 JIS Cable Guide AP-4+/05+105+0&4#9+014440%10. #% #6 #6 52#42#465.+5614 5 #%%5514+5 Page Page Page Dec/08 R.Esumi Mar/09 R.Esumi Dec/08 R.Esumi 14/Jul/09 R.Esumi 14/Jul/09 R.Esumi 26/Oct/09 R.Esumi Dec/08 R.Esumi Dec/08 R.Esumi Dec/08 R.Esumi Doppler Sonar