5. Maintenance

This chapter is intended for persons with skills in electrical and mechanical areas due to their training, experience and received instructions.

Personnel using the instructions in this chapter must be instructed of the regulations for the prevention of accidents, the operating conditions and safety regulations and their implementation.

Ensure in each case that the personnel are informed.

For maintenance work taking place at heights of over approx. 6 feet, use only ladders or similar equipment and working platforms intended for this purpose. At greater heights, the proper equipment for protection against falling must be worn.

Use only suitable lifting gear which is in proper working order and load suspension devices with sufficient carrying capacity. Do not stand or work under suspended loads!

Ensure that the electric motors/switch cabinets are sufficiently protected against moisture.

Use only suitable workshop equipment.

Before starting maintenance work, appoint a supervisor.

Inform the responsible personnel before maintenance work on the system is started.

Never operate the equipment when partially dismantled.

All maintenance and repair work not described in this chapter may only be carried out by Sterling service personnel or authorized personnel (appointed by Sterling).

LDisconnect the equipment from mains supply before starting maintenance procedures to ensure that it cannot be switched on unintentionally.

Depressurize all system sections of the equipment before carrying out any repair work.

Maintenance 8

Image 22
Contents Operating Instructions Single Conveyor Unit SSE-5 BL SSE 5 BL SSE 5 BL Parts and Service Department Table of contents Technical data Spare parts list SSE-2 General instructions SSE 5 BL Legal basis Explanations and informationFields of applications Safety instructions For your safety GeneralAssembly Maintenance OperationFor the operating safety of the equipment Putting into operation Checking the pipe system Adjusting the suction pipes If the conditions points 3 + 4 are metSetting the controller Switching off the unit Initial conveying operationsError and error correction When the malfunction has been corrected press the key Maintenance SSE 5 BL Maintenance intervals Servicing the conveyorObserve the direction of installation G Changing the sealing ring of the outlet flapAdjusting the flap switch Outlet flapCleaning the unit Order numberFilter cloth Wire cloth Functional description General Controller ControllerSSE 5 BL Transport, Assembly and Storage Transport and Packing AssemblyStorage Assembly instructions CSE 5 BL Assembly Mounting on the processing machine Mounting onto a machine hopperMounting onto mixing hoppers with lateral inlet Mounting onto dosing station DTMaterial feed Mounting the suction pipe MVPipework Electrical connectionInstallation of the flap switch signal line Installation of the signal line of the SKW optionalInstallation of the alarm indicating device optional Installing the accessories Compressed-air supplyTechnical data SSE 5/BL Dimension Sheet Spare parts list SSE-f/BL, 230 V, 50 Hz SSE-5/BL, 230 V, 50 Hz Pos Order no Designation Wear CodeAccessories Accessories Electrical manual SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL