Sterling SSE-5 BL operating instructions Adjusting the flap switch, Outlet flap

Page 26

SSE 5 BL

5.2.2. Adjusting the flap switch

Remove the connecting plug “flap switch” from the connection housing of the hopper.

Connect an ohmmeter to PINS 2 and 3 of the connecting plug “flap switch”.

Release the nuts (A) of the flap switch (B) until the support can be displaced.

Open the outlet flap (C) so far that the front tip of the outlet flap is approx. 30 mm (1.2") away from the sealing surface.

Displace the flap switch (B) until the contact of the magnet switch is closed.

Tighten the nuts (A) of the flap switch.

Check the adjustment:

In case of free hanging outlet flap (empty hopper loader) the contact of the magnet switch must be closed.

Figure 1: Outlet flap

If the outlet flap cannot be properly adjusted, replace the flap switch or the outlet flap with magnet.

Install the hopper.

& Order numbers

switch with plug:

ID 28839

outlet flap with magnet:

ID 23093

Maintenance 12

Image 26
Contents Operating Instructions Single Conveyor Unit SSE-5 BL SSE 5 BL SSE 5 BL Parts and Service Department Table of contents Technical data Spare parts list SSE-2 General instructions SSE 5 BL Fields of applications Explanations and informationLegal basis Safety instructions For your safety GeneralAssembly Maintenance OperationFor the operating safety of the equipment Putting into operation Checking the pipe system Adjusting the suction pipes If the conditions points 3 + 4 are metSetting the controller Switching off the unit Initial conveying operationsError and error correction When the malfunction has been corrected press the key Maintenance SSE 5 BL Maintenance intervals Servicing the conveyorObserve the direction of installation G Changing the sealing ring of the outlet flapAdjusting the flap switch Outlet flapCleaning the unit Order numberFilter cloth Wire cloth Functional description General Controller ControllerSSE 5 BL Transport, Assembly and Storage Storage AssemblyTransport and Packing Assembly instructions CSE 5 BL Assembly Mounting on the processing machine Mounting onto a machine hopperMounting onto mixing hoppers with lateral inlet Mounting onto dosing station DTMaterial feed Mounting the suction pipe MVPipework Electrical connectionInstallation of the flap switch signal line Installation of the signal line of the SKW optionalInstallation of the alarm indicating device optional Installing the accessories Compressed-air supplyTechnical data SSE 5/BL Dimension Sheet Spare parts list SSE-f/BL, 230 V, 50 Hz SSE-5/BL, 230 V, 50 Hz Pos Order no Designation Wear CodeAccessories Accessories Electrical manual SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL