8.6. Material feed

Suction pipes type MV may be tilted by approx. 45 degrees in either direction to the vertical. Additional fastening is not required.

When conveying from the bottom of storage containers (silos), a suction box with 1-3 suction pipes is required.

The connection of the suction pipes must be carried out with a piece of flexible line to provide sufficient movement.

Please observe that the length of the hose should not exceed 3 meters (10 feet). Push the free pipe end into the flexible line to a depth of approx. 4-5 cm (1.5" - 2"). Connect both parts by means of a hose clamp.

8.7. Mounting the suction pipe MV

The suction pipe consists of an inner pipe (A) and an outer pipe (B) which can be offset against each other.

Connect the inner pipe with the straight end to a flexible hose:

Push the free pipe end into the flexible line to a depth of approx. 4-5 cm (1.5" - 2"). Connect both parts by means of a hose clamp.

Please observe that the length of the hose should not exceed 3 meters (10 feet).

Please check that the outer pipe is not covered as it provides for unhindered access of ambient air.

FWhen conveying from silos, material hoppers and storage containers, a suction box with 1-3 suction pipes is required.

Figure 8: MV

Assembly instructions 26

Image 40
Contents Operating Instructions Single Conveyor Unit SSE-5 BL SSE 5 BL SSE 5 BL Parts and Service Department Table of contents Technical data Spare parts list SSE-2 General instructions SSE 5 BL Legal basis Explanations and informationFields of applications Safety instructions For your safety GeneralAssembly Maintenance OperationFor the operating safety of the equipment Putting into operation Checking the pipe system Adjusting the suction pipes If the conditions points 3 + 4 are metSetting the controller Switching off the unit Initial conveying operationsError and error correction When the malfunction has been corrected press the key Maintenance SSE 5 BL Maintenance intervals Servicing the conveyorObserve the direction of installation G Changing the sealing ring of the outlet flapAdjusting the flap switch Outlet flapCleaning the unit Order numberFilter cloth Wire cloth Functional description General Controller ControllerSSE 5 BL Transport, Assembly and Storage Transport and Packing AssemblyStorage Assembly instructions CSE 5 BL Assembly Mounting on the processing machine Mounting onto a machine hopperMounting onto mixing hoppers with lateral inlet Mounting onto dosing station DTMaterial feed Mounting the suction pipe MVPipework Electrical connectionInstallation of the flap switch signal line Installation of the signal line of the SKW optionalInstallation of the alarm indicating device optional Installing the accessories Compressed-air supplyTechnical data SSE 5/BL Dimension Sheet Spare parts list SSE-f/BL, 230 V, 50 Hz SSE-5/BL, 230 V, 50 Hz Pos Order no Designation Wear CodeAccessories Accessories Electrical manual SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL