6.2. Controller

The control system is mounted on the separator lid.

The setting for the conveying time and the line clear time are made via the keys (A1: “change-

over” key, A2: “arrow key”) on the front of the control system. The values which have been set will be displayed on the display (B). The values which have been set are maintained after the machine has been shut off.

3 LEDs indicate the respective modes of operation: cleaning (C), conveying (D), line clearing (E).

&The conveying time can be set from 1 to 99 seconds. The line clear time can be set from 0 to 99 seconds. The clearing time consists of 2 seconds.

The emptying time consists of 8 seconds.

When the unit is switched on all LEDs blink and the software version is displayed.

C

D

B

E

A1 A2

Figure 4: Controller

Functional description 17

Image 31
Contents Operating Instructions Single Conveyor Unit SSE-5 BL SSE 5 BL SSE 5 BL Parts and Service Department Table of contents Technical data Spare parts list SSE-2 General instructions SSE 5 BL Legal basis Explanations and informationFields of applications Safety instructions General For your safetyAssembly Operation MaintenanceFor the operating safety of the equipment Putting into operation Checking the pipe system If the conditions points 3 + 4 are met Adjusting the suction pipesSetting the controller Initial conveying operations Switching off the unitError and error correction When the malfunction has been corrected press the key Maintenance SSE 5 BL Servicing the conveyor Maintenance intervalsChanging the sealing ring of the outlet flap Observe the direction of installation GOutlet flap Adjusting the flap switchOrder number Cleaning the unitFilter cloth Wire cloth Functional description General Controller ControllerSSE 5 BL Transport, Assembly and Storage Transport and Packing AssemblyStorage Assembly instructions CSE 5 BL Assembly Mounting onto a machine hopper Mounting on the processing machineMounting onto dosing station DT Mounting onto mixing hoppers with lateral inletMounting the suction pipe MV Material feedElectrical connection PipeworkInstallation of the signal line of the SKW optional Installation of the flap switch signal lineInstallation of the alarm indicating device optional Compressed-air supply Installing the accessoriesTechnical data SSE 5/BL Dimension Sheet Spare parts list SSE-f/BL, 230 V, 50 Hz Pos Order no Designation Wear Code SSE-5/BL, 230 V, 50 HzAccessories Accessories Electrical manual SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL SSE 5 BL