7.Mount the side panels to the sides of the first and last battery cabinets:
a.Mount the hanger brackets to the top side of the battery cabinets using M4 screws (refer to Chapter 3, Figure 11 for location).
b.Hang the side panel on the hanger brackets and align it with the front and rear of the battery cabinet.
c.Secure the side panel at the bottom using M4 hex head screws.
8.Secure all battery cabinets by closing and latching the doors.
9.Secure the UPS by reinstalling safety shields and closing and latching the doors.
WARNING:
Initial closing of the battery cabinet breakers or the external battery disconnect should be performed only in the presence of authorized service personnel.
Completing the Installation Checklist
The final step in installing your battery cabinet is to complete the Installation Checklist. This checklist ensures that you have installed all hardware, cables, and other equipment. Completing all items on the checklist will ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain the original.
After completing your installation, a service representative will be able to verify the operation of your battery cabinet, and commission it to support your critical load. The service representative cannot perform any installation tasks other than verifying that the battery cabinet has been correctly installed. Service personnel may request a copy of the completed Installation Checklist to be sure you have completed all applicable equipment installation requirements.
NOTE:
The Installation Checklist MUST be completed prior to starting up the UPS system for the first time.
|
|
|