INSTALLATION | ||
|
|
|
OUTPUT CONNECTIONS
See Table A.1 for recommended IDEALARC®
TAbLE A.1
IDEALARC®
Cable at 100% Duty Cycle
Cable Length | Parallel Cables | Cable Size |
|
|
|
Lengths up to 150 ft. (46m) | 2 | 1/0 (53mm2) |
|
|
|
150 ft.(46m) to 200 ft (61m) | 2 | 2/0 (67mm2) |
|
|
|
200 ft.(61m) to 250 ft.(76m) | 2 | 3/0 (85mm2) |
|
|
|
ELECTRODE, WORK AND #21 LEAD
CONNECTIONS
A. Connect Electrode and Work Leads to
Output Terminals.
1.Set the ON/OFF toggle switch to OFF.
2.Locate the retractable strain relief loops directly below the output terminals in the lower right and lower left corners of the Case Front Assembly. See Figure A.6.
3.Pull out the retractable strain relief loops.
4.Insert the electrode lead through the loop directly below the desired polarity (positive or negative). Pull through enough cable to reach the output terminals.
FIGURE A.6 - Output Terminals.
5.Connect electrode lead to the desired terminal (positive/negative).
6.Tighten the output terminal nut with a wrench.
7.Connect the work lead to the other output terminal following steps
b. Connect #21 Work Sense Lead to Proper Terminal
There are two work sense lead connection points (+21 and