Hansol Multitech Uromat 3000 Central Beam Center of Bucky, Lengthwise to the tabletop, for this

Page 50

3.2Central Beam - Center of Bucky

Determine the deviation of the central beam.

Transverse to the tabletop, for this:

Caution:

Risk of an accident exists here because the tube unit must be loosened.

Remove the cover panel (Fig. 52/Pos. 6). Remove the mounting screws (Fig. 52/Pos. 1), remove the shims (Pos. 2) for the tube unit and insert them to compensate for any difference in the central beam. Reinstall the mounting screws (Pos. 1).

Lengthwise to the tabletop, for this:

Remove the cover panel (Fig. 53/Pos. 1). Correct the exposure position of the system using the software and the switch strike plate (Fig. 54/ Pos. 2) by the amount of the difference. Reinstall the cover panel (Fig. 53/Pos. 1).

Fig.53

Fig.54

3.3 Central Beam – Center of I.I.

Determine the deviation of the central beam.

Loosen the screws (Fig. 54/Pos. 1), correct the connector brackets (Pos. 3) by the amount of the difference and retighten the screws.

0116 7201

-50 of 90 -

06/00

Rev. 00 © 2000 Hans Pausch Röntgengerätebau Graf -Zeppelin-Str. 1 D-91056 Erlangen ALL RIGHTS RESERVED Ru

Image 50
Contents Installation Instructions Uromat Contents Not configured AdjustmentsTechnical Maintenance Component Dimensions General Safety InformationComponent Weights Packaging Dimensions and WeightsComponent Designations Dimensional Drawing, Right-handed Version FFADimensional Drawing, Left-handed Version FFA345 Drehachse Dimensional Drawing for Floor Mounting, Left-handed Version 0116 06/00 Required Test Equipment Power Line Connection DataRequired Special Tools Conditions for Transport and StorageCircuit Diagram, Contents of Circuit Diagram06/00 0116 Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Circuit Diagram, Collimator connection Uromat Component Designations for the Circuit DiagramSystem Location Component Function LED1 +A6 Terminal strip for Bucky Cassette box motor potentiometer Function Description of the Controller Boards CPU BoardBreaker Board Footswitch Board Control Unit Display BoardPreparations for Mounting Unpacking the UnitRemoving the Unit from the Pallet Installing the Unit Column Aligning the Unit Column Temporarily Connecting Line Power Installing the Tube Unit Support ArmPreinstalling the Tube Unit Collimator Combination Installing the Image Intensifier Laying the Collimator CablesLaying the High Voltage Cables To lay cables in the unit, 7 meters are requiredPage Making the Power Connection through the Generator Laying the I.I. CableInstalling the Measuring Chamber Installing the Grid Replacing the Grid Installing the Tilt Angle Display- Error DisplayInstalling the Cover Panels Installing the Monitor Support Arm OptionInstalling the Mount for the Flush Bowl Sealing the Table Frame Cover PanelAdjustment Tube Unit Support ArmLengthwise to the tabletop, for this Central Beam Center of BuckyCentral Beam Center Movement Path Potentiometer, Tabletop longitudinal I.I. Carriage System Potentiometer Movement Path Potentiometer, Tabletop transverseBucky Cassette Tray Movement Path Potentiometer Potentiometer 1 Table Tilt Movement Path Potentiometer 2 Table Tilt Movement PathTabletop Longitudinal Safety Switch Tabletop Transverse Safety Switch Not configuredTable Up Movement Path Switch Strike Plate Bucky Movement Path Safety Switch13 I.I. Carriage Movement Path Safety Switch Table Down Movement Path Switch Strike PlateSpindle Nut Safety Limit Switch 16 -20 Tilt Movement Safety Switch17 +88 Tilt Movement Safety Switch Raise-Lower Tabletop Belt Tension Accessory Sensor SwitchesTabletop longitudinal Belt Tension Cassette Carriage Drive Belt Tension Operation in the Service Mode EquipmentSetting Parameters ProcedureAdjusting the Axes StartupCollimator Basic Setting Format Setting the Collimator to the Cassette and I.I. FormatCassette Format Saving the Parameters in the PC Electronic Adjustment Parameters Setup ParametersTabletop long. Store yes/no 1/0 Technical Maintenance Mechanical and Electrical ChecksPreparations Page Function Check Page 176 Spare Parts, Overview41/43 40/41 /10 Spare Parts, Unit Column Right-handed, Left-handed Versions122 125 11 119 120 121 151 Spare Parts, Table Frame Tabletop, Right-handed Version128 135 185 136 Spare Parts, Table Frame Tabletop, Left-handed VersionSpare Parts, Tube Unit Support Right-handed Version 193 191 213 209 202 203 191 192 197 194 193 198 201 207 / 210209 207 / 210 Spare Parts, Tube Unit Support Left-handed VersionSpare Parts, Accessories 249 155 156Spare Parts List Pos DesignationPos Designation Pos Designation Pos Designation Pos Designation Troubleshooting Error Cause Corrective Measure NumberPage Board Replacement Version UpdateMaintenance Verification Location of Identification Labels Labeling Max kg/ 66 lb Overview of Labels