50PEC UNIT
START-UP CHECKLIST
CUSTOMER:___________________________ | JOB NAME: _______________________________________ | |
MODEL NO.:___________________________ | SERIAL NO.:____________________ | DATE:_________ |
I.PRE-START-UP
DOES THE UNIT VOLTAGE CORRESPOND WITH THE SUPPLY VOLTAGE AVAILABLE? (Y/N)
HAVE THE POWER AND CONTROL WIRING CONNECTIONS BEEN MADE AND TERMINALS TIGHT? (Y/N)
HAVE WATER CONNECTIONS BEEN MADE AND IS FLUID AVAILABLE AT HEAT EXCHANGER? (Y/N)
HAS PUMP BEEN TURNED ON AND ARE ISOLATION VALVES OPEN? (Y/N)
HAS CONDENSATE CONNECTION BEEN MADE AND IS A TRAP INSTALLED? (Y/N) IS AN AIR FILTER INSTALLED? (Y/N)
II.START-UP
IS FAN OPERATING WHEN COMPRESSOR OPERATES? (Y/N)
UNIT VOLTAGE — COOLING OPERATION
PHASE AB VOLTS PHASE AB AMPS
CONTROL VOLTAGE |
|
IS CONTROL VOLTAGE ABOVE 21.6 VOLTS? (Y/N) | . |
IF NOT, CHECK FOR PROPER TRANSFORMER CONNECTION.
TEMPERATURES
FILL IN THE ANALYSIS CHART ATTACHED.
COAXIAL HEAT | COOLING CYCLE: |
| F | WATER OUT |
| F |
| ft wg |
| gpm |
EXCHANGER | WATER IN |
|
|
|
| |||||
| HEATING CYCLE: |
| F | WATER OUT |
| F |
| ft wg |
| gpm |
| WATER IN |
|
|
|
| |||||
AIR COIL | COOLING CYCLE: |
| F | AIR OUT |
| F |
|
|
|
|
| AIR IN |
|
|
|
|
|
| |||
| HEATING CYCLE: |
| F | AIR OUT |
| F |
|
|
|
|
| AIR IN |
|
|
|
|
|
|