HP Performance Optimized Data Center (POD) 20cp manual Supported facility connections

Page 16

Supported facility connections

Environmental control system

The ECS developed for the HP water-cooled POD is a stand-alone control system that requires no external connections with an external site system, BMS, public or private Internet sites, cloud, or wireless system to properly control the POD operation.

The ECS includes Modbus TCP/IP connections through which a variety of data can be retrieved. These capabilities enable you to connect, at your expense, with the stand-alone ECS system to monitor the operating parameters of the POD. It is your responsibility (or your representative's or agent's responsibility) to integrate this communication capability into any existing BMS or monitoring system.

CAUTION: To ensure that alarm conditions can be identified and resolved, HP recommends that you remotely monitor all alarm conditions. Failure to monitor the alarm conditions can cause delays in appropriate action during an alarm condition.

Additional POD connections

The HP POD 20c provides various connection points to your facility. It is your responsibility to facilitate these connections. HP can make these connections when specifically contracted to deliver these services and a Scope of Work has been drafted, reviewed, and signed for delivery services. Available POD connections include the following:

Life safety systems o EPO

o Fire detection

o Fire suppression

Site communication o Phone

o Access control

Networking—IT connections

Connection portals

Networking and connection portals are located on the cargo end of the HP POD 20c. Each HP POD 20c has six 6.35-cm (2.5-in) portals for customer data connection. These portals are provided to allow the customer to make connections to the HP POD 20c.

Supported facility connections 16

Image 16
Contents Abstract Part Number March EditionPage Contents Project coordination Site planning HP POD 20c installation HP POD 20c site assessment checklistOverview Safety and NEC complianceAbout this document Site safety and security Feature SpecificationSite assessment Site preparationElectrical power capacities critical IT power HP POD 20c capacitiesHP POD 20c capacity limitations Overall system capacitiesHP POD 20c weight Dimensions and clearancesSite requirements Site padSite requirements Future expansions Grounding requirements Requirement Location Specification UtilitiesHumidifier water supply Drainage Chilled water supply Piping materials Power infrastructure installationSite electrical system Electrical power system configuration Supported facility connections Environmental control systemAdditional POD connections Connection portalsHumidifier End view shownFire, safety, and access notifications HP POD 20c access controlDemarcation box Supported facility connections Areas prone to lightning or power surges Environmental considerationsEnvironmental risks Cold weatherSite plan requirements and actions Completing a site assessmentHP Site Preparation Drawing Package Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationHP POD 20c site readiness checklist Installation prerequisitesAppendix B Preparing for delivery Pre-delivery tasksGeneral Water Supply Description Initial Description InitialChilled Water Supply Description Initial Power Requirements Description Initial General Description InitialAppendix C Regulatory compliance notices Safety and NEC complianceHP POD 20c regulatory compliance Safety and regulatory compliance Warranty information Glossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Index Index
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 38 pages 28.4 Kb