HP Performance Optimized Data Center (POD) 20cp Site requirements, Site pad, HP POD 20c weight

Page 8

Site requirements

Site pad

The structural design of the HP POD 20c site pad must be based on the specific weight load of the complete POD solution with IT installed, as well as any additional equipment. During design calculations, HP recommends that you provide structural support along the entire perimeter of the POD and use the maximum allowable POD weight.

Upon installation, the POD structure must be leveled to less than or equal to 0.5º. Shimming is allowed around the perimeter of the POD to ensure that the POD remains level. If significant shimming is required, shims should be spaced no less than 1.2 m (4 ft) apart to ensure sufficient load transfer. Shims are not included.

IMPORTANT: The HP POD 20c is designed for ground level installation. If you install the HP POD 20c on an elevated surface, verify that the minimum height requirements for circuit breaker actuators are considered per national, regional, and local regulations and electrical codes. The area in front of the outside panels must include a work platform.

HP POD 20c weight

IMPORTANT: The weight provided is a minimum and an absolute maximum rated weight. The total weight of the HP POD 20c differs based on the IT equipment and optional components purchased and installed.

The overall weight might significantly vary depending on the final customer-chosen solution for the HP POD 20c. Each site pad must meet the weight requirements of the equipment that is expected to be installed.

The HP POD 20c must be installed on a surface capable of supporting the following weights:

HP POD 20c with no IT equipment installed—Approximately 7,711 kg (17,000 lb)

HP POD 20c with IT equipment installed—Maximum 22,680 kg (50,000 lb)

Dimensions and clearances

The selected site for the HP POD 20c must be large enough to install, service, maintain, and provide space for potential growth or expansion with additional PODs.

Site requirements 8

Image 8
Contents Abstract Part Number March EditionPage Contents Project coordination Site planning HP POD 20c installation HP POD 20c site assessment checklist About this document Safety and NEC compliance Overview Site safety and security Feature SpecificationSite assessment Site preparationElectrical power capacities critical IT power HP POD 20c capacitiesHP POD 20c capacity limitations Overall system capacitiesHP POD 20c weight Dimensions and clearancesSite requirements Site padSite requirements Future expansions Grounding requirements Requirement Location Specification UtilitiesHumidifier water supply DrainageChilled water supply Site electrical system Power infrastructure installationPiping materials Electrical power system configuration Supported facility connections Environmental control systemAdditional POD connections Connection portalsHumidifier End view shownDemarcation box HP POD 20c access controlFire, safety, and access notifications Supported facility connections Areas prone to lightning or power surges Environmental considerationsEnvironmental risks Cold weatherSite plan requirements and actions Completing a site assessmentHP Site Preparation Drawing Package Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationHP POD 20c site readiness checklist Installation prerequisitesAppendix B Preparing for delivery Pre-delivery tasksChilled Water Supply Description Initial Description InitialGeneral Water Supply Description Initial Power Requirements Description Initial General Description InitialHP POD 20c regulatory compliance Safety and NEC complianceAppendix C Regulatory compliance notices Safety and regulatory compliance Warranty information Glossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Index Index
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 38 pages 28.4 Kb