Environmental considerations

Environmental risks

Avoid placing the HP POD 20c directly along a drainage path or in an area prone to flooding.

Verify that the HP POD 20c is properly grounded in accordance with national, regional, and local regulations, ordinances, codes, and the product specifications.

Cold weather

The HP POD 20c requires a site chilled water supply and return, humidifier supply and drain, and condensate drains. Extreme cold weather can cause damage to the supply and drain lines. Evaluate the following for additional cold weather protection:

Regional location of the HP POD 20c

Exposure of the supply and drain lines to extreme cold temperatures

Extreme cold weather can affect crane and lifting operations. When temperatures drop below -12.2°C (10°F), appropriate consideration must be made with respect to shock loading, crane hydraulics, and possible de-rating of the crane.

Areas prone to lightning or power surges

The HP POD 20c structure and internal components are all bonded together. A common Grounding Electrode Conductor Connection point is provided. Proper bonding and grounding of the HP POD 20c minimizes the effects of a lightning strike. A surge protection device is provided on the HP POD 20c input connection to protect the HP POD 20c electrical system from voltage transients. If your site is in an area that is subject to frequent lightning strikes, the HP POD 20c must be protected in accordance with NFPA 70 (NA) and IEC (EMEA and APJ). HP recommends that you contact a certified lightning protection consultant.

Seismic activity

If your site is in an area that has frequent seismic activity, HP recommends that you contact a seismic activity consultant. If your site is in an area that has high vibration level, HP recommends that you contact a vibration isolation consultant. You must specify the method of anchoring the HP POD 20c, if necessary.

Environmental considerations 20

Image 20
Contents Abstract Part Number March EditionPage Contents Project coordination Site planning HP POD 20c installation HP POD 20c site assessment checklistAbout this document Safety and NEC complianceOverview Site safety and security Feature SpecificationSite assessment Site preparationElectrical power capacities critical IT power HP POD 20c capacitiesHP POD 20c capacity limitations Overall system capacitiesHP POD 20c weight Dimensions and clearancesSite requirements Site padSite requirements Future expansions Grounding requirements Requirement Location Specification UtilitiesHumidifier water supply DrainageChilled water supply Site electrical system Power infrastructure installationPiping materials Electrical power system configuration Supported facility connections Environmental control systemAdditional POD connections Connection portalsHumidifier End view shownDemarcation box HP POD 20c access controlFire, safety, and access notifications Supported facility connections Areas prone to lightning or power surges Environmental considerationsEnvironmental risks Cold weatherSite plan requirements and actions Completing a site assessmentHP Site Preparation Drawing Package Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationHP POD 20c site readiness checklist Installation prerequisitesAppendix B Preparing for delivery Pre-delivery tasksChilled Water Supply Description Initial Description InitialGeneral Water Supply Description Initial Power Requirements Description Initial General Description InitialHP POD 20c regulatory compliance Safety and NEC complianceAppendix C Regulatory compliance notices Safety and regulatory compliance Warranty information Glossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Index Index
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 38 pages 28.4 Kb