HP Performance Optimized Data Center (POD) 20cp manual Appendix a HP site assessment

Page 25

Appendix A: HP site assessment

HP POD 20c site assessment checklist

During a survey of the readiness of a proposed customer site for the HP POD 20c, the site is inspected for the following:

Accessibility of machinery for the transportation and installation of the HP POD 20c

Assessment of the suitability of the site infrastructure for installing the HP POD 20c and for supporting infrastructure preparation and serviceability requirements

HP responsibilities

Item

Description

 

Yes

No

N/A

Initial

 

 

 

 

 

 

 

 

 

1. Engagement plan

Develop an engagement plan with specific requirements

 

 

 

 

 

 

 

relating to the proposed installation site.

 

 

 

 

 

 

2. Site visits

Schedule site visits on mutually acceptable dates, during

 

 

 

 

 

 

 

normal HP business hours.

 

 

 

 

 

 

3. Test equipment

Document any test equipment used in the customer report.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4. Installation site

Review and discuss the proposed installation site with the

 

 

 

 

 

 

review

customer. This initial review includes physical examination of

 

 

 

 

 

 

the proposed installation site and, at the sole discretion of

 

 

 

 

 

 

 

HP, can include physical measurements of the area size and

 

 

 

 

 

 

clearances.

 

 

 

 

 

 

5. Indoor/outdoor

Identify whether the HP POD 20c installation is indoors or

 

 

 

 

 

 

installation

outdoors as this can affect the degree and type of

 

 

 

 

 

 

 

infrastructure required and the mounting needs.

 

 

 

 

 

 

6. Site pad

Inspect the proposed installation site to assess

 

 

 

 

 

 

 

compliance with the HP POD 20c mounting

 

 

 

 

 

 

 

specifications. Ensure that the customer is fully aware of

 

 

 

 

 

 

the following requirements:

 

 

 

 

 

 

 

Proper support capabilities must exist. If the customer

 

 

 

 

 

 

 

intends to edge or point load on the utility and cargo

 

 

 

 

 

 

 

ends, there must be support in the center to prevent

 

 

 

 

 

 

 

deflection.

 

 

 

 

 

 

 

Upon installation, the POD structure must be leveled to

 

 

 

 

 

 

0.5º, which can be checked at that time with a surveyor’s

 

 

 

 

 

 

transit.

 

 

 

 

 

 

 

Shimming is allowed around the perimeter of the POD.

 

 

 

 

 

 

 

Place shims in increments across the length of the HP

 

 

 

 

 

 

 

POD 20c to ensure that the HP POD 20c is level. If

 

 

 

 

 

 

 

significant shimming is required, shims should be spaced

 

 

 

 

 

 

no less than 1.2 m (4 ft) apart to ensure sufficient load

 

 

 

 

 

 

 

transfer.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7. Materials and

Visually inspect the materials and construction at the

 

 

 

 

 

 

construction

proposed installation site to identify issues that can impact

 

 

 

 

 

 

inspection

the HP POD 20c installation. Verify that the area is adequate

 

 

 

 

 

 

for truck delivery, staging, and crane location.

 

 

 

 

 

 

 

 

Appendix A: HP site assessment 25

Image 25
Contents Part Number March Edition AbstractPage Contents HP POD 20c site assessment checklist Project coordination Site planning HP POD 20c installationOverview Safety and NEC complianceAbout this document Feature Specification Site safety and securitySite assessment Site preparationHP POD 20c capacities Electrical power capacities critical IT powerHP POD 20c capacity limitations Overall system capacitiesDimensions and clearances HP POD 20c weightSite requirements Site padSite requirements Future expansions Grounding requirements Utilities Requirement Location SpecificationHumidifier water supply DrainageChilled water supply Piping materials Power infrastructure installationSite electrical system Electrical power system configuration Environmental control system Supported facility connectionsAdditional POD connections Connection portalsEnd view shown HumidifierFire, safety, and access notifications HP POD 20c access controlDemarcation box Supported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 20c installationHP POD 20c storage requirements Assembly equipment locations DescriptionAdditional structures Appendix a HP site assessment HP POD 20c site assessment checklistUsed as the basis for the evaluation. The delivery path is Description Yes InitialInformation Customer responsibilities Description InitialInstallation prerequisites HP POD 20c site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksGeneral Water Supply Description Initial Description InitialChilled Water Supply Description Initial General Description Initial Power Requirements Description InitialAppendix C Regulatory compliance notices Safety and NEC complianceHP POD 20c regulatory compliance Safety and regulatory compliance Warranty information Glossary Very early smoke detection apparatus Uninterruptible power systemDocumentation feedback Index Index