HP Performance Optimized Data Center (POD) 20cp manual Site planning, HP POD 20c installation

Page 22

Ensure that the site safety and security programs are properly administered.

Interface directly with the HP installation project manager to ensure clear lines of communication during the installation and commissioning processes.

Site planning

A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 20c installation process. When creating a site plan, consider the following information:

HP POD 20c site requirements detailed in this document

HP POD 20c site preparation drawing package

HP POD 20c readiness checklist ("HP POD 20c site readiness checklist" on page 28)

HP POD 20c installation (on page 22)

The HP team can assist you by answering questions and help to guiding you throughout the process.

HP POD 20c installation

HP POD 20c installation includes the following:

Installation equipment staging (on page 22)

HP POD 20c lifting layout (on page 22)

HP POD 20c storage requirements (on page 23)

Additional structures (on page 24)

Installation equipment staging

Staging for the following items must be identified and considered:

Truck and component staging

Installation equipment staging

Site traffic

Regulatory or local permits

HP POD 20c lifting layout

When preparing a site plan, identify where to place the HP POD 20c and the equipment that is used for assembly. The following figure shows an HP POD 20c assembly site and includes:

HP POD 20c location

Crane location

Site plan requirements and actions 22

Image 22
Contents Abstract Part Number March EditionPage Contents Project coordination Site planning HP POD 20c installation HP POD 20c site assessment checklistOverview Safety and NEC complianceAbout this document Site assessment Site safety and securityFeature Specification Site preparationHP POD 20c capacity limitations Electrical power capacities critical IT powerHP POD 20c capacities Overall system capacitiesSite requirements HP POD 20c weightDimensions and clearances Site padSite requirements Future expansions Grounding requirements Humidifier water supply Requirement Location SpecificationUtilities DrainageChilled water supply Piping materials Power infrastructure installationSite electrical system Electrical power system configuration Additional POD connections Supported facility connectionsEnvironmental control system Connection portalsHumidifier End view shownFire, safety, and access notifications HP POD 20c access controlDemarcation box Supported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationAppendix B Preparing for delivery HP POD 20c site readiness checklistInstallation prerequisites Pre-delivery tasksGeneral Water Supply Description Initial Description InitialChilled Water Supply Description Initial Power Requirements Description Initial General Description InitialAppendix C Regulatory compliance notices Safety and NEC complianceHP POD 20c regulatory compliance Safety and regulatory compliance Warranty information Glossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Index Index