HP Performance Optimized Data Center (POD) 20cp manual Site plan requirements and actions

Page 21

Site plan requirements and actions

Completing a site assessment

HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 20c. Consult with HP to schedule a site assessment.

A standard site assessment visit includes the following tasks:

Selecting an appropriate site for the HP POD 20c

Assessing the proposed site for: o Measurements for clearances

o Infrastructure for the final solution o Access to utilities

o Site pad

o Installation considerations, including locations for delivery trucks, large installation equipment (such as cranes), and storage

o Electrical infrastructure

o Chilled water infrastructure

o Facility network and access control systems

Developing an engagement plan and verifying customer contacts

Discussing future development and growth plans

For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 25)."

HP Site Preparation Drawing Package

After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings contain information to assist you and your MEP team to prepare the site for POD installation. If there are areas of special interest, HP can work directly with your MEP team to provide additional assistance.

Zoning and permit requirements

You are responsible for compliance of the overall installation in accordance with all local and national regulations, ordinances, codes, and the product specifications.

Project coordination

Your Project Manager must perform the following tasks:

Coordinate with all trades prior to installation to ensure that trade conflicts are resolved.

Coordinate the installation and integration of all systems.

Site plan requirements and actions 21

Image 21
Contents Part Number March Edition AbstractPage Contents HP POD 20c site assessment checklist Project coordination Site planning HP POD 20c installationSafety and NEC compliance OverviewAbout this document Feature Specification Site safety and securitySite assessment Site preparationHP POD 20c capacities Electrical power capacities critical IT powerHP POD 20c capacity limitations Overall system capacitiesDimensions and clearances HP POD 20c weightSite requirements Site padSite requirements Future expansions Grounding requirements Utilities Requirement Location SpecificationHumidifier water supply DrainageChilled water supply Power infrastructure installation Piping materialsSite electrical system Electrical power system configuration Environmental control system Supported facility connectionsAdditional POD connections Connection portalsEnd view shown HumidifierHP POD 20c access control Fire, safety, and access notificationsDemarcation box Supported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 20c installationHP POD 20c storage requirements Assembly equipment locations DescriptionAdditional structures Appendix a HP site assessment HP POD 20c site assessment checklistUsed as the basis for the evaluation. The delivery path is Description Yes InitialInformation Customer responsibilities Description InitialInstallation prerequisites HP POD 20c site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksDescription Initial General Water Supply Description InitialChilled Water Supply Description Initial General Description Initial Power Requirements Description InitialSafety and NEC compliance Appendix C Regulatory compliance noticesHP POD 20c regulatory compliance Safety and regulatory compliance Warranty information Glossary Very early smoke detection apparatus Uninterruptible power systemDocumentation feedback Index Index
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 38 pages 28.4 Kb