HP Performance Optimized Data Center (POD) 20cp manual Humidifier, End view shown

Page 17

End view shown

Humidifier

A dedicated water supply and approved drainage is required for the humidifier. For more information about the humidifier, see the HP Performance Optimized Datacenter 20c User Guide that is provided with the HP POD 20c.

The following image shows the location of the humidifier drain and water supply. Side view shown

IMPORTANT: Confirm with the AHJ that condensate water and rain water can be mixed in the same drainage.

Supported facility connections 17

Image 17
Contents Part Number March Edition AbstractPage Contents HP POD 20c site assessment checklist Project coordination Site planning HP POD 20c installationAbout this document Safety and NEC complianceOverview Feature Specification Site safety and securitySite assessment Site preparationHP POD 20c capacities Electrical power capacities critical IT powerHP POD 20c capacity limitations Overall system capacitiesDimensions and clearances HP POD 20c weightSite requirements Site padSite requirements Future expansions Grounding requirements Utilities Requirement Location SpecificationHumidifier water supply DrainageChilled water supply Site electrical system Power infrastructure installationPiping materials Electrical power system configuration Environmental control system Supported facility connectionsAdditional POD connections Connection portalsEnd view shown HumidifierDemarcation box HP POD 20c access controlFire, safety, and access notifications Supported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 20c installationHP POD 20c storage requirements Assembly equipment locations DescriptionAdditional structures Appendix a HP site assessment HP POD 20c site assessment checklistUsed as the basis for the evaluation. The delivery path is Description Yes InitialInformation Customer responsibilities Description InitialInstallation prerequisites HP POD 20c site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksChilled Water Supply Description Initial Description InitialGeneral Water Supply Description Initial General Description Initial Power Requirements Description InitialHP POD 20c regulatory compliance Safety and NEC complianceAppendix C Regulatory compliance notices Safety and regulatory compliance Warranty information Glossary Very early smoke detection apparatus Uninterruptible power systemDocumentation feedback Index Index
Related manuals
Manual 86 pages 43.14 Kb Manual 22 pages 15.98 Kb Manual 81 pages 57.33 Kb Manual 38 pages 28.4 Kb