HP Performance Optimized Data Center (POD) 20cp manual Power Requirements Description Initial

Page 30

Item

 

Description

Initial

 

 

 

 

2

 

Verify that the chilled water supply temperature meets the minimum POD chilled water supply

 

 

 

temperature of 12°C (55°F).

 

3

 

Verify that a sufficient chilled water flow rate is available.

 

4

 

If necessary, verify that the customer-required chilled water return temperatures can be

 

 

 

attained.

 

Power Requirements

 

 

 

 

Item

 

Description

Initial

 

 

 

 

1

 

Verify that the short circuit analysis, arc flash, and circuit breaker coordination studies are

 

 

 

complete. Verify power work is completed according to the approved conduit routing

 

 

 

drawings that show the exact routes, plan view, sections, and elevations.

 

2

 

Verify that temporary site power for installation and construction is planned and available, if

 

 

 

applicable.

 

3

 

Verify that adequate site power exists per the HP POD 20c requirements.

 

General

 

 

 

 

 

Item

 

Description

Initial

 

 

 

 

1

 

Verify the utility connection to the HP POD 20c and any required metering equipment.

 

2

 

Verify the third-party commissioning services that might be required by the owner.

 

3

 

Verify that the HP Project Team coordinates with other site construction activities.

 

Appendix B: Preparing for delivery 30

Image 30
Contents Abstract Part Number March EditionPage Contents Project coordination Site planning HP POD 20c installation HP POD 20c site assessment checklistSafety and NEC compliance OverviewAbout this document Site assessment Site safety and securityFeature Specification Site preparationHP POD 20c capacity limitations Electrical power capacities critical IT powerHP POD 20c capacities Overall system capacitiesSite requirements HP POD 20c weightDimensions and clearances Site padSite requirements Future expansions Grounding requirements Humidifier water supply Requirement Location SpecificationUtilities DrainageChilled water supply Power infrastructure installation Piping materialsSite electrical system Electrical power system configuration Additional POD connections Supported facility connectionsEnvironmental control system Connection portalsHumidifier End view shownHP POD 20c access control Fire, safety, and access notificationsDemarcation box Supported facility connections Environmental risks Areas prone to lightning or power surgesEnvironmental considerations Cold weatherHP Site Preparation Drawing Package Site plan requirements and actionsCompleting a site assessment Zoning and permit requirementsHP POD 20c installation Site planningAssembly equipment locations Description HP POD 20c storage requirementsAdditional structures HP POD 20c site assessment checklist Appendix a HP site assessmentDescription Yes Initial Used as the basis for the evaluation. The delivery path isCustomer responsibilities Description Initial InformationAppendix B Preparing for delivery HP POD 20c site readiness checklistInstallation prerequisites Pre-delivery tasksDescription Initial General Water Supply Description InitialChilled Water Supply Description Initial Power Requirements Description Initial General Description InitialSafety and NEC compliance Appendix C Regulatory compliance noticesHP POD 20c regulatory compliance Safety and regulatory compliance Warranty information Glossary Uninterruptible power system Very early smoke detection apparatusDocumentation feedback Index Index