HP Performance Optimized Data Center (POD) 20cp manual HP POD 20c storage requirements

Page 23

Assembly equipment locations

Item

Description

 

 

1

Crane

2

Reach

3

Truck

4

Area clear for scissors lift and forklift

HP POD 20c lifting requirements

WARNING: The only approved method for lifting the HP POD 20c is the use of a spreader bar harness. Lifting an HP POD 20c in any other manner can cause damage to the HP POD 20c and void your warranty. The harness and lifting connections must be perpendicular to the lifting blocks.

HP POD 20c storage requirements

If the site is not ready for assembly and operation, determine a location for storage when creating the site plan.

CAUTION: The HP POD 20c must maintain 20% relative humidity to minimize condensation and oxidation within the HP POD 20c.

CAUTION: While being stored, the HP POD 20c must be kept in a level position even if stored on a trailer.

Changes in ambient temperatures can cause condensation in a non-operational HP POD 20c. If the HP POD 20c is placed in storage or is in non-operating mode for over 72 hours, HP recommends using one of the following methods to minimize condensation and oxidation within the HP POD 20c:

Desiccant unit

Desiccant material

Heater with a fan

Air conditioner with a heater strip

Consult with HP Services to determine the most effective method.

Site plan requirements and actions 23

Image 23
Contents Part Number March Edition AbstractPage Contents HP POD 20c site assessment checklist Project coordination Site planning HP POD 20c installationAbout this document Safety and NEC complianceOverview Site preparation Site safety and securityFeature Specification Site assessmentOverall system capacities Electrical power capacities critical IT powerHP POD 20c capacities HP POD 20c capacity limitationsSite pad HP POD 20c weightDimensions and clearances Site requirementsSite requirements Future expansions Grounding requirements Drainage Requirement Location SpecificationUtilities Humidifier water supplyChilled water supply Site electrical system Power infrastructure installationPiping materials Electrical power system configuration Connection portals Supported facility connectionsEnvironmental control system Additional POD connectionsEnd view shown HumidifierDemarcation box HP POD 20c access controlFire, safety, and access notifications Supported facility connections Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental risksZoning and permit requirements Site plan requirements and actionsCompleting a site assessment HP Site Preparation Drawing PackageSite planning HP POD 20c installationHP POD 20c storage requirements Assembly equipment locations DescriptionAdditional structures Appendix a HP site assessment HP POD 20c site assessment checklistUsed as the basis for the evaluation. The delivery path is Description Yes InitialInformation Customer responsibilities Description InitialPre-delivery tasks HP POD 20c site readiness checklistInstallation prerequisites Appendix B Preparing for deliveryChilled Water Supply Description Initial Description InitialGeneral Water Supply Description Initial General Description Initial Power Requirements Description InitialHP POD 20c regulatory compliance Safety and NEC complianceAppendix C Regulatory compliance notices Safety and regulatory compliance Warranty information Glossary Very early smoke detection apparatus Uninterruptible power systemDocumentation feedback Index Index