8Maintenance and annual startup

Table 8A_Service and Maintenance Schedules

Service technician

(see the following pages for instructions)

 

General:

 

 

 

 

• Address reported problems

 

• Inspect

interior;

clean and vacuum if

 

 

necessary;

 

 

 

Check for leaks (water, gas, flue)

 

• Examine venting system

 

• Check system

water

pressure/system

 

 

piping/expansion tank

 

 

Check control settings

 

 

• Check wiring and connections

 

Flame inspection (stable, uniform)

 

• Check flue gas passageways

Startup

• Inspect and clean the burner

• Perform

start-up

checkout and

 

 

 

performance verification per Section 6 -

Annual

 

Start-up.

 

 

 

If

combustion

or

performance

 

 

indicate need:

 

 

 

• Clean heat exchanger

 

 

• Remove and wash burner

 

 

 

 

 

 

Owner maintenance

(see the User’s Information Manual for instructions)

 

• Check appliance area

 

• Check pressure/temperature

 

gauge

 

 

Daily

 

 

 

 

 

 

Monthly

• Check vent piping

 

 

 

 

 

• Check relief valve

 

 

 

Periodically

• Test low water cutoff (if used)

 

 

 

 

• Reset button (low water cutoff)

 

 

Every

• Check appliance piping (gas and

water) for leaks

 

 

 

6 months

 

 

 

 

• Operate relief valve

 

 

 

 

End

•Shut

appliance

down (unless

boiler

used for

domestic hot

 

of season

water)

 

 

months

 

 

 

 

 

 

 

54

Image 54
Contents Models 90,000 500,000 Btu/hr Contents Please read before proceeding Checking equipmentCodes Ratings Copper-fin =B=R RatingCopper-fin Specifications Copper-fin How it works Gas connection pipeModels CWN270 Front View Model CWN399 Front View 422 Determine unit location Location of unitDetermine boiler location 3Combustion Air Direct from Outside6Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Venting Conventional Negative Draft Venting SystemVent Pipe Sizes Venting Vertical Vent Termination Clearances Less from Ridge From Parapet WallSidewall Venting Masonry Chimney InstallationVent Materials NumberAutomatic Vent Damper 7CB with Vent Damper and Vent Damper Terminal BlockGas Connection Gas connectionsGas Supply Gas Pressure Test Manifold PressureInstall Piping to Control Gas PipingGas Manifold Pressure Adjustment Procedure Clockwise to raise regulator gas pressure, counterclockwiseChecking Gas Supply Pressure 4Gas Supply PressureCombination Gas Valves Venting of Combination Gas ValvesTwo Stage Burner Control System Water Flow Switch if equipped Hydronic pipingRelief Valve Minimum Required Flow For Heating Boiler Typical Heating Boiler InstallationsLow Water Cutoff if equipped General Plumbing RulesSystem Temperature Rise Chart Piping of the Boiler SystemWater Connections Heating Boilers Only Heat Exchanger Pressure Drop ChartCirculator Pump Specifications Circulator Pump RequirementsPrimary/Secondary Boiler Piping Three Way Valves Boiler Flow RatesPrimary / Secondary Piping 4Primary / Secondary Piping of a Single BoilerNot to Exceed 4 Pipe DIA or MAX. of 12 Apart 8Multiple Boilers Zoned with Circulators Power Venter Connection to Terminal Strip Terminal Strip WiringBoiler Operating Temperature Control Electrical connectionsTemperature Adjustment Pump Wiring for a Heating BoilerOperating Temperature Control Maximum SET Point Determination Locating Temperature ControlTemperature Control Settings Maximum Set Point DeterminationMulti-Purpose Temperature Sensor Temperature Control SensorsInlet Water Temperature Sensor Outdoor Air Temperature SensorOutdoor Air Reset Option Installation of a Remote Sensor Boiler ApplicationInstallation of a Tank Sensor Water Heater Application Additional Temperature Controls Blocked Vent and Flame Roll-Out / Flame Interlock Switch Manual Reset High Water Temperature Limit ControlPre-start Checklist Start-upInitial Start-up Lighting Instructions 1Gas Valve 90,000 270,000 Btu/hr ModelsSafety Shutoff Test For Standing Pilot Ignition System To Turn OFF GAS to ApplianceOperating Instructions Freeze Protection Safety Shutoff Test for Spark Ignition Pilot SystemIntermittent Pilot Spark Ignition System F9/M9 To Turn Off Gas to ApplianceWater Treatment Freeze Protection for a Heating Boiler System if requiredDomestic water heaters Required Temperature RiseRequired Temperature Rise Domestic Water Heaters 90,000 500,000 Btu/hr ModelsWater Chemistry Softened Water SystemsPump Operation 1Single water heatersingle tank 2Single water heatermultiple tank 3Multiple water heatersingle tank Minimum Pump Performance Remote Sensor InstallationThermostat Settings Heat Exchanger5Danger Warning Thermal Expansion Water Flow Switch if equippedPressure Only Relief Valve Cathodic ProtectionOwner maintenance Maintenance and annual startupService technician See the User’s Information Manual for instructionsMaintenance Check Expansion Tank Check Relief ValveCombustion Air Adjustment Check All WiringCheck Control Settings Perform Start-up and ChecksInspect and Clean Burner Heat Exchanger / Burner AccessInspection and Cleaning Procedure Inspection of Heat Exchanger Waterways Pilot Flame Adjustment ProcedureClear Area Water Circulating PumpReview with owner Gas Train and ControlsTroubleshooting Pilot or replace Wiring Diagram F1 Unit DiagramsSchematic Diagram F1 Unit 90,000 270,000 Btu/hr ModelsSchematic Diagram F9 Unit Wiring Diagram F9 Unit315,000 399,999 Btu/hr Models Diagrams Diagrams Page Revision a ECO #C06290 initial release CFA-I-S Rev a 09/10