FAN MOTOR TEST PROCEDURE
A simple test can be used to test the fan motor operation. A fully charged 9V battery will be required for this procedure.
FAN MOTOR TEST
This is a test that will verify that the motor does operate.
1. Verify main (240 volt) power if OFF to unit.
2. Remove both wires (brown and black) from the J2 terminal on the fan motor control.
3. Room thermostat should be in OFF position (Unit in idle mode − no heating or cooling demands)
4. Turn main power (240 volt) ON to unit.
5. Connect 9 Volt batter to outdoor fan motor plugs as noted in pic- ture below..
6. Outdoor fan motor should run at a reduced fan speed.
7. If Outdoor fan motor does not run, then replace fan motor assem- bly.

FAN MOTOR CONTROL

BLACK LEAD

BROWN LEAD

 

 

 

J2

 

 

 

J2

REMOVE BOTH LEADS

COM

 

FROM J2 TERMINALS

PARK

 

BLACK LEAD

OUTPWMFAN

 

BROWN LEAD

 

BROWN LEAD

BLACK LEAD

V

CONNECT FAN MOTOR BLACK

COMMON WIRE TO 9V BATTERY

NEGATIVE TERMINAL

CONNECT FAN MOTOR WIRE TO 9V BATTERY POSITIVE TERMINAL

506510−01

NEGATIVE TERMINAL

POSITIVE TERMINAL

FULLY CHARGED 9V BATTERY

Figure 25. Fan Motor Test

Page 46

Image 46
Contents Shipping and Packing List Table of ContentsGeneral AIR ConditionerModel Number Identification Unit Dimensions − Inches mm and Parts ArrangementSide View Access View Base with Elongated LegsTypical Unit Parts Arrangement PLUMBING, Switches and Sensor ComponentsControl BOX Operating Service Valves Operating Gauge Set and Service ValvesUsing Manifold Gauge SET Torque RequirementsOperating Ball Type Service Valve To Access Service PortOperating Angle Type Service Valve Reinstall Stem CapRecovering Recovering Refrigerant from Existing SystemMinimum Clearance Between TWO Units New Outdoor Unit PlacementClearance on ALL Sides Minimum Clearance Above Unit Positioning ConsiderationsStabilizing Unit on Uneven Surfaces Elevating the UnitRoof Mounting Slab Mounting at Ground Level Outside Unit PlacementElevated Slab Mounting using Feet Extenders Stabilizing Unit on Uneven SurfacesAccess and Louvered Removing and Installing PanelsAccess Panel Removal Louvered Panel InstallationNew or Replacement Line Set Refrigerant Line SETLine SET Brazing Uncased Coil Shown FlushingFlushing the System Line SET and Indoor Coil 1Equalizer Line Installation Sensing Bulb InstallationFlushing Line SET and Indoor Coil 2 Leak Testing the System Installing Isolation GrommetsLeak Test Line SET and Indoor CoilEvacuating Evacuating the SystemElectrical Size Circuit and Install Disconnect2INSTALL Thermostat 24VAC Transformer3ROUTE Control Wires 4ROUTE High Voltage and Ground WiresTypical XC17 Wiring Main Control Jumpers and Terminals Main Control AGEMain Control Jumpers and Terminals FANField Control Wiring Flat metal jumperOn−board link Servicing Units Delivered Void of Charge Connections for Testing and ChargingGauge SET Unit Start−UpIndoor Coil AirflowAction Requirements WeighCharge METHOD? Determine by Calculating System Charge for Outdoor Unit Void of ChargeSubcooling ApproachTest and Charge Method Operating and Temperature Pressures HFC−410A Temperature Fahrenheit PsigSystem Operation Test Pins Function Ambient Sensor Temperature / Resistance Range High Discharge Sensor Temperature / Resistance Range Main Control LED Alert Codes Sensor Temperature / Resistance RangeResetting LED Alert Codes System LED Alert CodesAlert Status Compressor LED Alert Codes Detected in RUN High Pressure Switch Operation Low Pressure Switch Operation High Discharge Temperature Sensor Operation FAN Motor Control and Start UP MaintenanceVerifying Jumper Settings J2 Verifying LED Status CodesLED Codes and Sequence of Operations Fan Motor Board Unit LED CodesControl Panel Testing for External Power to Fan Control Fan Motor Test FAN Motor Surge Protection Fan Motor Surge Protection DeviceCooling Mode XC17 Start−Up and Performance ChecklistStart UP Checks Subcooling