Raypak 0090B 0135B installation instructions Electrical Wiring, Fig.#

Page 14

ELECTRICAL WIRING

The electrical power supply requirement for these boilers is 115 volts, 60 Hz. Field wiring connections and electrical grounding must comply with the local codes, or in the absence of local codes, with the National Electrical Code, ANSI/NFPA 70-1987.Provide a sepa- rate fused circuit from the main electrical panel to the boiler, and a disconnecting means within sight of the boiler.

Remove the control box cover and make the power supply connections in the field wiring compartment. (See general location of controls drawing on page 18). The pump is supplied and factory wired to operate with the boiler. The "TH" wire leads are for the room thermostat or zone valve connections.

The room thermostat should be installed in accordance with the manufacturer's instructions. The thermostat heat anticipator should be set at 1.0 ampere (automatic ignition) and 0.60 ampere (standing pilot) for single zone installations. For multi-zone applications, the heat anticipator setting should be based on the ampere load in the thermostat circuit.

NOTE: If it is necessary to replace any of the original wiring, it must be replaced with 105°C wire or its equivalent, except 150° black wire must be replaced with 150°C wire or its equivalent. See wiring diagram key for 150°C wire indication.

WIRING DIAGRAM KEY

Fig.# 8096.2

14

Image 14
Contents Operating Installation Instructions For Your SafetyContents Receiving Equipment General SpecificationsSpecifications and Dimensions Mounting Base Installation ProceduresCode Requirements Clearance RequirementsModel Sq. In. of Free Area 0030, 0042 100 Venting ConnectionsCommon Vents Fig.#Vent Damper Installation LocationMounting Installing the Vent Damper in Horizontal & Vertical VentsD80D General Wiring Diagram Vent Damper Flair DamperWater Connections & System Piping GAS PRESSURE-SPECIFICATIONSGAS Supply Connections Typical Piping Single Zone PipingZone Heating with Indirect Domestic HOT Water Supply Multiple Zones with Circulators Multiple Zones with Zone ValvesElectrical Wiring Fig.#Wiring Diagram Standing Pilot 24 V 2 Stage Fig. # 2223eWiring Diagramintermittent Ignition Device IID Models 30, 42 Wiring Diagram Intermittent Ignition Device IID Fig. #2358Wiring Diagram Single Zone Taco Valve Wiring Diagram System with 3 Zone Pumps Fig. #2223.2e Wiring Diagram Standing Pilot With Low Water Cut Off Device Control BOX Component Locations Models 135 Servicing ProceduresGeneral Location of Controls Sequence of Operation Intermittent Ignition Device IIDSTART-UP Procedures Filling the SystemLighting the Boiler What to do if YOU Smell GASHoneywell Pilot Robertshaw Pilot For Automatic Ignition ModelsSystem Shut Down Procedure To Turn OFF GAS to BoilerFor Automatic Ignition Systems Flame Failure Inspection Procedures BurnersSafe Shutdown Tests Limit Action Main Burner FlameMain Burner and Orifice Removal Raypak Tube Cleaning KITBurner Drawer Removal Repair SectionHeat Exchanger RE-ASSEMBLY Combustion Chamber RemovalTrouble Shooting Guide Important NoticePiping ADJUSTMENTS/REPLACEMENTS of Components Replacement Parts List RAYPAK, INCBypass valve supplied on sizes H-0135 and H-0180 only Page Venting