Frame Installation

Check rough opening as follows and correct if necessary:

Sub-floor to be flat, level, and clean. Sill must be supported throughout its entire length.

All four corners to be square. Check with a framing square.

Framing and walls to be plumb. Use a 6-foot level to check both sides of opening.

All wall surfaces to be straight and sides parallel.

Opening to be correct size. Allow 3/8" on sides and ½" at head.

Wall

straight?

Check each side both ways.

Wall straight?

Check all four corners with square.

Check floor under sill.

6

Image 7
Contents Double Unit Assembly & Installation Screen sold separately Active Panel Inactive Panel Screw Chart Install Sill CAP Base If APPLICABLE, Install TOP-HUNG Screen TrackLAY Frame Components Onto Work Area Attach Head to Jambs Attach Sill to JambsApply Corner Pads to Sealing FIN Drip CAP InstallationFrame Installation SET Unit Into Rough Opening Apply Silicone Sealant to Sill and FinsPlumb Side Jambs Level SillApply Sealant to Inactive Door Riser Secure Frame in Rough OpeningInstall Anchor Blocks Install Stationary PanelAdjust Rollers Install Active PanelAttach Inactive Interlock Install Active InterlockInsert Panel Bumper Handle InstallationAttach Strike Plate Prep Door for Foot Bolt Install Sill CAP TOPAttach Foot Bolt Sliding Screen Door Install Foot Bolt KeeperInsert Plugs Attach Jamb CoverActive panel edge Dia holes 1 deep Towards Page Finishing Instructions Jamb Extension Information WEATHERPROOF, Finish and MaintainInterior Casing Attachment Sizing Information Door Handing Guide Patiodoorsystems