Final Check and Trial Operation

To complete the installation, perform the following checks and tests to ensure that the air conditioner operates correctly.

Check the followings:

Strength of the installation site

Tightness of pipe connection to detect gas leak

Electric wiring connection

Heat-resistant insulation of the pipe

Drainage

Grounding conductor connection

Correct operation (follow the steps below)

ENGLISH

1. Press the Power button and check the following:

The indicator on the indoor unit lights up.

2.Press the Mode button to select Cool or Heat mode.

In Cool mode, use Temp + or - button and set the temperature at 16°C.

In Heat mode, use Temp + or - button and set the temperature at 30°C.

• Approximately 3~5 minutes later, outdoor unit will start to operate and the Cool or Warm air will blow out.

• After 12 minutes of stationary condition check the indoor unit air treatment:

Cooling mode (indoor unit check) Heating mode (indoor unit check)

Inlet air temp. - Outlet air temp : From 10°C to 12°C ( indicative delta T)

Outlet air temp. - Inlet air temp : From 11°C to 14°C (indicative delta T)

3. Press the Air swingbutton and check the following:

4. Press the Power button to stop the operation.

• When you complete the installation successfully, hand over this manual to the user for storage in a handy and safe place.

Pump down procedure (when removing the product)

1.Turn on the air conditioner and select Cool mode to run the compressor for 3 minutes.

2. Release the valve caps on High and Low pressure side.

3. Use L wrench to close the valve on the high pressure side.

4. Approximately 2 minutes after, close the valve on the low pressure side.

5. Stop operation of the air conditioner.

6. Disconnect the pipes.

39

Image 39
Contents Air Conditioner Contents Wall socket Safety precautionsImportant safety symbols and precautions Follow directionsFor Using For Cleaning Operation ranges Checking before useDisplay Power buttonChecking the name of the parts Main partsRemote controller buttons Checking the remote controllerInserting the batteries Remote controller displayBattery changing time Storing the remote controllerBasic function Press Button to adjust the temperaturePosition you prefer Using the Turbo functionPress the Air swing button on the remote controller Circulate the airMode Press the button Press the button to set the time Press the Set/Cancel button to active it onFrom the moment you have set the timer Using the Smart Saver functionTimer 1 hour Timer 5 hoursUsing the Quiet function Heat exchanger Cleaning the indoor unitCleaning the outdoor unit heat exchanger Opening the panelDry the Ai lter in a ventilated area Cleaning the air conditionerClean the Air Slide it downPeriodical checks Maintaining the air conditionerTroubleshooting Outdoor unit Heat exchanger during Heat mode in winter If may not be aConnection Model Name Included Models Remark General informationWon’t be considered in-warranty and charged to end user Choosing the installation locationInstalling the unit Power supply line, fuse or circuit breakerModel Outdoor UnitWhen installing more than 1 outdoor unit  When the air outlet is towards the wallTop view Side view Accessories Accessories in the indoor unit caseAccessories in the outdoor unit case Tools for test operations Fixing the installation plateOptional accessories Tools required for installation General ToolsConnecting the assembly cable Connecting the cableFix the indoor unit Each wire is labeled with the corresponding terminal number Extend the assembly cable if necessaryThen pull it out through the appropriate hole Smooth the cut edgesConnect the pipes Purging the indoor unitCutting or extending the pipe Unscrew the caps at the end of each pipeOuter Diameter Correct InclinedCracked Applying the following torqueChanging direction of the drain hose Drain hose installationExcessive torque can be cause of gas leakage Purging the connected pipesAdding Refrigerant Covered by the Kyoto Protocol 1975Leak test with nitrogen before opening valves Performing the gas leak testsTo check for gas leaks on the outdoor unit To check for gas leaks on the indoor unitProperly Model Outdoor unit installed on the wall by rackFixing the outdoor unit in place Part without insulation on the end of the pipesFinal Check and Trial Operation Pump down procedure when removing the productPress the Power button and check the following Press the Mode button to select Cool or Heat modeHow to connect your extended power cables Questions or COMMENTS?