COMPLETING THE INSTALLATION
Final Check and Trial Operation
AQU/R
AQU/R
AQE
AQE
To complete the installation, perform the following checks and tests to ensure that the air conditioner operates correctly.
1Check the followings:
Strength of the installation site
Tightness of pipe connection to detect gas leak
Electric wiring connection
Drainage
Grounding conductor connection
Correct operation (follow the steps below)
2Press the button and check the following:
The indicator on the indoor unit lights up.
The airflow blade opens and the fan gears up for operation.
3Press the button to select Cool or Heat mode.
In Cool mode, use Temp or button and set the temperature at 16°C.
In Heat mode, use Temp or button and set the temperature at 30°C.
Note Approximately 3~5 minutes later, outdoor unit will start to operate and the Cool or Warm air will blow out.
After 12 minutes of stationary condition check the indoor unit air treatment:
Cooling mode (indoor unit check)
Heating mode (indoor unit check)
In heating mode, the indoor fan motor can remain off to avoid cold air blown into conditioned space.
4Press the button and check the following: The airflow blades work properly.
5Press the button to stop the operation.