Samsung AQ24UGAN, AQ09UGDN manual Final Check and Trial Operation

Page 22

COMPLETING THE INSTALLATION

Final Check and Trial Operation

AQU/R

AQU/R

AQE

AQE

To complete the installation, perform the following checks and tests to ensure that the air conditioner operates correctly.

1Check the followings:

Strength of the installation site

Tightness of pipe connection to detect gas leak

Electric wiring connection

Heat-resistant insulation of the pipe

Drainage

Grounding conductor connection

Correct operation (follow the steps below)

2Press the button and check the following:

The indicator on the indoor unit lights up.

The airflow blade opens and the fan gears up for operation.

3Press the button to select Cool or Heat mode.

InCool mode, use Temp or button and set the temperature at 16°C.

InHeat mode, use Temp or button and set the temperature at 30°C.

Note Approximately 3~5 minutes later, outdoor unit will start to operate and the Cool or Warm air will blow out.

 After 12 minutes of stationary condition check the indoor unit air treatment:

Cooling mode (indoor unit check) --> Inlet air temp. - Outlet air temp: From 10°K to 12°K ( indicative delta T)

Heating mode (indoor unit check) --> Outlet air temp. - Inlet air temp: From 11°K to 14°K (indicative delta T)

In heating mode, the indoor fan motor can remain off to avoid cold air blown into conditioned space.

4Press the button and check the following: The airflow blades work properly.

5Press the button to stop the operation.

E-22

Vivaldi_IM_30271A_E_11.07.09.indd 22

2009-11-7 13:57:18

Image 22
Contents Vivaldi IM30271AE11.07.09.indd 2009-11-7 Contents Safety Precautions EnglishMinor personal injury or property Choosing the Installation Location Model Figure Description Top view Side viewWhen installing more than 1 outdoor unit Accessories in the Outdoor Unit Case AccessoriesAccessories in the Indoor Unit Case Following accessories are supplied with the air conditionerFixing the Installation Plate Direction of pipeConnecting the Assembly Cable Model Power cable Interconnection Type GLIndoor unit Outdoor unitOuter Diameter Torque kgfcm DO not Wall UP the Pipe ConnectionPurging the Indoor Unit Cutting or Extending the Pipe Depth a Flaring Size BInstalling and Connecting the Drain Hose of the Indoor Unit Drain hose installationChanging Direction of the Drain Hose Change the direction only when it is necessary Direction of the drained water Installing and Connecting the Drain Hose of the Outdoor Unit You should purge the air in the indoor unit and in the pipe Purging the Connected PipesWith a Global Warming Potential GWP = Reduction of cooling capacity and malfunctionGWP value Add refrigerant charge according to table below If you use a pipe Then 1975Leak Test with Nitrogen before opening valves Performing the Gas Leak TestsTo check for gas leaks on Leak Test with R410A after opening valvesFixing the Indoor Unit in Place Fixing the Outdoor Unit in PlaceFinal Check and Trial Operation Providing Information for User Pump Down Procedure When removing the productStorage in a handy and safe place Vivaldi IM30271AE11.07.09.indd 2009-11-7 Installation Manual Cooling and Heating
Related manuals
Manual 31 pages 36.44 Kb Manual 32 pages 17.61 Kb Manual 32 pages 60.27 Kb Manual 30 pages 51.71 Kb Manual 32 pages 35.17 Kb Manual 32 pages 6.86 Kb Manual 34 pages 7.54 Kb Manual 32 pages 51.3 Kb Manual 33 pages 37.87 Kb Manual 31 pages 55.87 Kb Manual 31 pages 51.06 Kb