New Buck Corporation 21 Floor Protection, Convert specification to R-value

Page 32

Floor Protection:

Floor protection must be 3/8” minimum thickness non-combustible material or equivalent.

How to use alternate materials and how to calculate equivalent thickness.

An easy means of determining if a proposed alternate floor protector meets requirements listed in the appliance manual is to follow this procedure:

1. Convert specification to R-value:

R-value is given—no conversion is needed.

K– factor is given with a required thickness (T) in inches: C-factor is given: R=1/C

2. Determine the R-value of the proposed alternate floor protector.

Use the formula in step (1) to convert values not expressed as “R”

For multiple layers, add R-values of each layer to determine the overall R-value.

3.If the overall R-value of the system is grater than the R-value of the specified floor protec- tor, the alternate is acceptable.

Example:

The specified floor protector should be 3/4” thick material with a K-factor of 0.84.

The proposed alternate is 4” brick with a C-factor of 1.25 over 1/8” mineral board with a K-factor of 0.29.

Step (a): Use formula above to convert specification to R-value. R= 1/K x T = 1/0.84 x .75 = 0.893

Step (b): Calculate R of proposed system. 4” brick of C=1.25, therefore Rbrick = 1/C = 1/1.25

=0.80 1/8” mineral board of K = 0.29, therefore Rmin.bd. =1/029 x0.125 = 0.431

Step (c): Compare proposed system R of 1.231 to specified R of 0.893. Since proposed system R is greater than required , the system is acceptable.

Definitions:

Thermal conductance = C = Btu = W (hr)(ft²)(°F) (m²)(°K)

Thermal conductance = K = (Btu)(inch) =

W =

(Btu)

(hr)(ft²)(°f)

(m)(°K)

(hr)(tf)(°F)

Thermal conductance = R = (ft²)(hr)(°F) = (m²)(°K)

Btu W

Install in accordance with 24 CFR, Part 3280 (HUD).

30

Image 32
Contents Buck Stove MODEL NON-CATALYTICUNITMODEL NON-CAT Page TABLE OF CONTENTS READ THIS FIRST IMPORTANT INSTRUCTIONS INSTALLATION, OPERATION, ANDMAINTENANCE INSTRUCTIONS MODEL SECTION INTRODUCTIONMODEL MASONRY INSERT INSTALLATIONSECTION Floor Protection MASONRY INSERT INSTALLATION OPTIONS POSSIBLE TOOLS NEEDED FOR INSTALLATIONINSTALLATION PREPARATION AIRTIGHT INSU LATED CLEAN OUT REMOVE DAMPER OR WIRE IT OPENSTARTER PIPE SEAL TRIM PANELS AND UNDER FRONT OF STOVE UNIT WITH INSULATION OR HIGHPOSITIONING THE HEATER POSITIONINGMOUNTING THE TRIM PANELS FIGURE 3 MOUNTING TRIM PANELSFINAL CHECK Page SECTION PRE-FABINSERT INSTALLATION PREPARING THE STOVE FOR INSTALLATION Chimney1. Convert specification to R-value Floor ProtectionHOW TO LOCATE CHIMNEY EXIT, AND INSTALL Residential InstallationPREPARING THE ROOM HEATER LOCATION CHIMNEYModel 21 minimum clearance to combustibles NOTE For minimum clearances See Page 17, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential Installation Model 21 minimum clearance to combustibles Residential and Mobile Home Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLWithout close clearance shield and pipe shield NOTE For minimum clearances See Page 19, Figureany listed 2100 UL 103 HT. TYPE Chimney Model 21 minimum clearance to combustiblesD. Vertical Wall Exit using 6 DVL Close Clearance Pipe, and Elbow, and any Listed 2100 UL HT chimney and Listed 2100 UL HT T-Boxassembly HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation Listed 2100 UL HT T-Boxassembly Model 21 minimum clearance to combustiblesNOTE For minimum clearances See Page 23, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation any listed 2100 UL 103 HT. TYPE Chimney Model 21 minimum clearance to combustiblesNOTE For minimum clearances See Page 25, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation Listed 2100 UL HT T-Boxassembly OUT SIDE AIR INSTALLATION Page FINAL CHECK Chimney SECTION ALCOVE INSTALLATION AND CLEARANCESPREPARING THE STOVE FOR INSTALLATION 1. Convert specification to R-value Floor ProtectionAlcove Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLModel 21 minimum clearance to combustibles ALCOVE INSTALLATION AND CLEARANCESany listed 2100 UL 103 HT. TYPE Chimney Installation of Optional Close Clearance Shields Installation of Optional Pipe ShieldPipe Shield Loosen these top shield screws 13/16” TYP 1” TYP 1/4” TYPFINAL CHECK SECTION WOOD HEATER SAFETY SECTION OPERATION BUILDING A FIRESECTION TROUBLESHOOTING PROBLEMSOLUTION POSSIBLE CAUSEPOSSIBLE CAUSE PROBLEMSOLUTION WARRANTY TIME PERIODS PROCEDURENEW BUCK CORPORATION NBC PRODUCTS COVEREDCONDITIONS AND EXCLUSIONS OTHER RIGHTS