Select an installation location that will give the best airflow from the front of the

heater to the remainder of the home.

PREPARING THE STOVE FOR INSTALLATION

1.Inspect the unit for any obvious physical damage.

2.Plug the power cord into a 115V AC outlet to test the motor and fan when optional motor is being used. “Do not run power cord under unit or in high traffic areas”.

3.Check the primary air draft control to ensure that it slides freely.

4.Remove any items from within the firebox. Spread a dropcloth on the floor behind the heater. Next, tilt the heater so that the back is on the drop cloth.

5.If leg kit is to be used follow steps 1-6.

6.Then obtain four legs, attach the legs to holes in bottom of unit with bolts and washers supplied with the leg kit. (See Figure 20.)

7.Open the corresponding freestanding kit and obtain the stand. Place the stand against the bottom of the heater (angle side to heater).Center stand front to rear ,and also center the stand left and right ,and mark screw locations on bottom of the stove through outer holes of stand mounting angles. Set stand aside and drill four 7/32" holes in heater bottom.Then mount stand to bottom of heater with screws provided. (See Figure 21).

8.Obtain four (4) 3/16" self-tapping screws and secure the stand to the heater.

9.Reposition the heater to the upright position.

10.

Figure 20

Chimney

Figure 21 Manual backgroundManual backgroundManual backgroundManual backgroundManual background

This model is designed for connection to the following listed 2100º UL103 HT chimneys and parts. Follow chimneys manufacturer's instructions carefully.

Simpson Duravent

Metal Fab

Security

Airjet

Selkirk Metal Bestos

Jakes Evans

This room heater must be converted to (1) a chimney complying with the requirements for Type HT chimneys in the Standard for chimneys, Factory-Built, Residential, Type and Building Heating Appliance, UL 103, or (2) a code approved masonry chimney with a flue liner.

29

Image 31
Contents MODEL NON-CAT MODEL NON-CATALYTICUNITBuck Stove Page TABLE OF CONTENTS MAINTENANCE INSTRUCTIONS MODEL INSTALLATION, OPERATION, ANDREAD THIS FIRST IMPORTANT INSTRUCTIONS INTRODUCTION SECTIONSECTION MASONRY INSERT INSTALLATIONMODEL Floor Protection INSTALLATION PREPARATION POSSIBLE TOOLS NEEDED FOR INSTALLATIONMASONRY INSERT INSTALLATION OPTIONS FRONT OF STOVE UNIT WITH INSULATION OR HIGH AIRTIGHT INSU LATED CLEAN OUT REMOVE DAMPEROR WIRE IT OPEN STARTER PIPE SEAL TRIM PANELS AND UNDERFIGURE 3 MOUNTING TRIM PANELS POSITIONING THE HEATERPOSITIONING MOUNTING THE TRIM PANELSFINAL CHECK Page SECTION PRE-FABINSERT INSTALLATION Chimney PREPARING THE STOVE FOR INSTALLATIONFloor Protection 1. Convert specification to R-valueCHIMNEY HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential Installation PREPARING THE ROOM HEATER LOCATIONModel 21 minimum clearance to combustibles Residential Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLNOTE For minimum clearances See Page 17, Figure Model 21 minimum clearance to combustibles NOTE For minimum clearances See Page 19, Figure Residential and Mobile Home InstallationHOW TO LOCATE CHIMNEY EXIT, AND INSTALL Without close clearance shield and pipe shieldModel 21 minimum clearance to combustibles any listed 2100 UL 103 HT. TYPE ChimneyResidential and Mobile Home Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLD. Vertical Wall Exit using 6 DVL Close Clearance Pipe, and Elbow, and any Listed 2100 UL HT chimney and Listed 2100 UL HT T-Boxassembly Model 21 minimum clearance to combustibles Listed 2100 UL HT T-BoxassemblyResidential and Mobile Home Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLNOTE For minimum clearances See Page 23, Figure Model 21 minimum clearance to combustibles any listed 2100 UL 103 HT. TYPE ChimneyResidential and Mobile Home Installation HOW TO LOCATE CHIMNEY EXIT, AND INSTALLNOTE For minimum clearances See Page 25, Figure Listed 2100 UL HT T-Boxassembly OUT SIDE AIR INSTALLATION Page FINAL CHECK PREPARING THE STOVE FOR INSTALLATION SECTION ALCOVE INSTALLATION AND CLEARANCESChimney Floor Protection 1. Convert specification to R-valueHOW TO LOCATE CHIMNEY EXIT, AND INSTALL Alcove Installationany listed 2100 UL 103 HT. TYPE Chimney ALCOVE INSTALLATION AND CLEARANCESModel 21 minimum clearance to combustibles 13/16” TYP 1” TYP 1/4” TYP Installation of Optional Close Clearance ShieldsInstallation of Optional Pipe Shield Pipe Shield Loosen these top shield screwsFINAL CHECK SECTION WOOD HEATER SAFETY BUILDING A FIRE SECTION OPERATIONPOSSIBLE CAUSE SECTION TROUBLESHOOTINGPROBLEM SOLUTIONSOLUTION PROBLEMPOSSIBLE CAUSE PRODUCTS COVERED WARRANTY TIME PERIODSPROCEDURE NEW BUCK CORPORATION NBCOTHER RIGHTS CONDITIONS AND EXCLUSIONS