New Buck Corporation 21 installation instructions Final Check

Page 11
FINAL CHECK

10.If direct connect or positive connect kit is not used, follow instructions in (mounting trim panels, steps 1-4c) on (Page 8).

11.Mount top trim panel by drilling mounting holes in center of trim panel mounting brackets, with top end side of top panel overlapping side panel.

12.Using insulation provided, peel and stick to back of panels overlapping fireplace dimensions by 1” on each side and top. (See Page 8, Figure 3).

13.Next using high heat silicone or furnace cement run heavy bead of caulking around where panels meet the stove. (See Figure 4).

14.Slide the unit back into the fireplace. Check to be sure that the trim panels (and brass) are properly positioned and lie flat against the front of the fireplace. If panels are out of position, slide the unit out and reset by loosening the mounting screws and repositioning in the slot. With bar, lift stove in front. Place insulation across front and the surface of hearth or bottom of fireplace, to make complete seal.

15.To check seal of panels, use candle flame and go around the entire area sealed by silicone and insulation. If flame leans toward inside of fireplace, add additional insulation. This ensures an airtight seal.

SILICONE

SCREW

FINAL CHECK

FIGURE 4

1.Recheck the specified clearances.

2.Remove all foreign material from the firebox area.

3.Open the primary air draft.

4.Plug the power cord into a 115V AC outlet if optional motor is being used.

5.Place rumpled pieces of newspaper in the stove. Light it and close the doors. Ensure that the stove draws properly through the primary draft.

6.Check for smoke leaks around the doors.

7.Open the door and check for smoke escaping from the front of the stove. Smoking usually indicates a defective or poorly positioned chimney. Some chimneys with a marginal draft can be preheated by lighting newspaper and holding it near the open damper with a poker or fire tong. Once the chimney heats up, a proper draft can usually be obtained.

If a thorough review of the Troubleshooting Guide in the rear of the manual does not reveal the problem, contact your dealer for assistance.

9

Image 11
Contents Buck Stove MODEL NON-CATALYTICUNITMODEL NON-CAT Page TABLE OF CONTENTS READ THIS FIRST IMPORTANT INSTRUCTIONS INSTALLATION, OPERATION, ANDMAINTENANCE INSTRUCTIONS MODEL INTRODUCTION SECTIONMODEL MASONRY INSERT INSTALLATIONSECTION Floor Protection MASONRY INSERT INSTALLATION OPTIONS POSSIBLE TOOLS NEEDED FOR INSTALLATIONINSTALLATION PREPARATION FRONT OF STOVE UNIT WITH INSULATION OR HIGH AIRTIGHT INSU LATED CLEAN OUT REMOVE DAMPEROR WIRE IT OPEN STARTER PIPE SEAL TRIM PANELS AND UNDERFIGURE 3 MOUNTING TRIM PANELS POSITIONING THE HEATERPOSITIONING MOUNTING THE TRIM PANELSFINAL CHECK Page SECTION PRE-FABINSERT INSTALLATION Chimney PREPARING THE STOVE FOR INSTALLATIONFloor Protection 1. Convert specification to R-valueCHIMNEY HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential Installation PREPARING THE ROOM HEATER LOCATIONModel 21 minimum clearance to combustibles NOTE For minimum clearances See Page 17, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential Installation Model 21 minimum clearance to combustibles NOTE For minimum clearances See Page 19, Figure Residential and Mobile Home InstallationHOW TO LOCATE CHIMNEY EXIT, AND INSTALL Without close clearance shield and pipe shieldModel 21 minimum clearance to combustibles any listed 2100 UL 103 HT. TYPE ChimneyD. Vertical Wall Exit using 6 DVL Close Clearance Pipe, and Elbow, and any Listed 2100 UL HT chimney and Listed 2100 UL HT T-Boxassembly HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation Model 21 minimum clearance to combustibles Listed 2100 UL HT T-BoxassemblyNOTE For minimum clearances See Page 23, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation Model 21 minimum clearance to combustibles any listed 2100 UL 103 HT. TYPE ChimneyNOTE For minimum clearances See Page 25, Figure HOW TO LOCATE CHIMNEY EXIT, AND INSTALLResidential and Mobile Home Installation Listed 2100 UL HT T-Boxassembly OUT SIDE AIR INSTALLATION Page FINAL CHECK Chimney SECTION ALCOVE INSTALLATION AND CLEARANCESPREPARING THE STOVE FOR INSTALLATION Floor Protection 1. Convert specification to R-valueHOW TO LOCATE CHIMNEY EXIT, AND INSTALL Alcove InstallationModel 21 minimum clearance to combustibles ALCOVE INSTALLATION AND CLEARANCESany listed 2100 UL 103 HT. TYPE Chimney 13/16” TYP 1” TYP 1/4” TYP Installation of Optional Close Clearance ShieldsInstallation of Optional Pipe Shield Pipe Shield Loosen these top shield screwsFINAL CHECK SECTION WOOD HEATER SAFETY BUILDING A FIRE SECTION OPERATIONPOSSIBLE CAUSE SECTION TROUBLESHOOTINGPROBLEM SOLUTIONPOSSIBLE CAUSE PROBLEMSOLUTION PRODUCTS COVERED WARRANTY TIME PERIODSPROCEDURE NEW BUCK CORPORATION NBCOTHER RIGHTS CONDITIONS AND EXCLUSIONS