C. Vertical Penetration Framing

WARNING

Fire Hazard

Keep loose materials or blown insulation from touching the vent pipe.

National building codes recommend using attic shield to keep loose materials/ blown insulation from contacting vent.

Hearth & Home Technologies requires the use of an attic shield.

Installing the Ceiling Firestop

Frame an opening 10 inches by 10 inches whenever the vent system penetrates a ceiling/floor (see Figure 6.4).

Frame the area with the same sized lumber as used in ceiling/floor joist.

When installing a top vent vertical termination appliance the hole should be directly above the appliance, unless the flue is offset.

Do not pack insulation around the vent. Insulation must be kept away from the pipe.

Installing Attic Shield

Note: An additional ceiling firestop is not required if attic shield is used.

• Frame opening for attic shield.

ATTIC ABOVE

10 IN. (254 MM)

10 IN.

(254 MM)

HOLE SHOULD MEASURE

10 IN. X 10 IN.

(254 MM X 254 MM)

INSIDE TO INSIDE

Figure 6.4

• Attic shield may be installed above or

 

 

 

below ceiling (see Figure 6.5).

 

 

• Secure with three fasteners on each

BEND TABS IN

 

 

side.

AROUND PIPE

 

 

 

 

Fold tabs at top of attic shield in toward

3 FASTENERS

 

 

vent pipe. Tabs must keep vent pipe

PER SIDE

 

 

 

 

 

centered within shield.

 

 

Field construct additional shield height if

 

 

 

insulation is deeper than height of attic

ATTIC SHIELD INSTALLED

ATTIC SHIELD INSTALLED

 

shield.

BELOW CEILING

ABOVE CEILING

 

 

Figure 6.5 Installing the Attic Shield

 

 

Heat & Glo • Cerona-36, Cerona-422106-900 Rev. F • 04/08

19

Image 19 Contents
What to do if you smell gas ModelsModel Number Serial Number Homeowner Reference InformationTable of Contents Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsRead all of the instructions before starting the insta Installation to ensure maximum safety and benefitGetting Started Tools and Supplies NeededSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance Chase724 425 406 279 Mantel ProjectionsHearth Extension Hearth Extension DimensionsVent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Alcove ApplicationsTo Install the Heat Shield Install Support BracketsContinue Adding Vent Components Measuring Standards Vent Information and DiagramsVent Table Key Use of Elbows Top Vent Horizontal Termination One Elbow Vent Diagrams Two Elbows 152 mm 914 mm 305 mm 610 mm 10 ft Top Vent Horizontal Termination Three ElbowsTop Vent Vertical Termination Straight up Vertical Venting V1 = 50 ft. Max .2 m305 mm 610 mm 914 mm 10 ft Top Vent Horizontal Termination Two ElbowsCombustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingInstalling Attic Shield Installing the Ceiling FirestopVertical Penetration Framing Appliance Preparation Removing Non-combustible Facing Mate- rial AssemblySecuring and Leveling the Appliance Diagram shows .2 the location of the nailing tabsProvided to secure the appliance to the framing members Complete Installation of Non-combustible Facing Material Installing Flue RestrictorsAssembling Pipe Sections Installing Vent PipeAssembly of Vent Sections Attaching Vent to the Firebox AssemblyAssembling DVP-12A Slip Sections Assembling Minimum Installations MI SectionsHorizontal Sections Disassembly of Vent SectionsSecuring the Vent Sections Vertical SectionsHeat shield DVP-HSM-B must be used Installing Heat Shield and Horizontal Termination CapInstalling the Horizontal Termination Cap Heat Shield Requirements for Horizontal Terminationflue of the pipe see Figure Installing Roof Flashing and Vertical Ter- mination Cap18 Assembling the Storm Collar Around the Pipe Assembling and Installing Storm CollarFuel Conversions Gas Connection Gas InformationGas Pressures High Altitude Installations Optional Accessories Requirements Recommendation for WireIntellifire Ignition System Wiring Connecting to the ApplianceProperly grounded Not operate unlessJunction Box Detail Junction Box InstallationStep Finishing Non-combustible Facing Material Facing MaterialMounting stone eye brow ATRIMSTONE-36, ATRIMSTONE-42 Finishing Material OptionsFinishing Material Thickness from 3/4 in. to 1-1/4 Finishing Material Thickness greater than 1-1/4 inch10 Fireplace sitting on combustible surface Ember Placement Appliance SetupClean the Appliance AccessoriesPositioning the Logs Model Cerona-36 Log Assembly LOGS-Cerona36Heat & Glo Cerona-36, Cerona-42 2106-900 Rev. F 04/08 Model Cerona-42 Step Air Shutter Setting Glass AssemblyGrilles and Trim Before Lighting Appliance Operating InstructionsThis appliance has an Intellifire ignition system Final inspection by Lighting Appliance IPI IgnitionInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Intellifire Ignition System TroubleshootingSympton Possible Cause Corrective Action Symptom Possible Cause Corrective Action Maintaining and Servicing Appliance Maintenance TasksDoors, Surrounds Inspect Maintenance TasksReference Materials Appliance Dimension DiagramModel Cerona-36 Model Cerona-42 DVP vent components Vent Components DiagramsDVP-TRAP COOL-ADD Not for use with these models Service Parts Log Set AssemblyPart number list on following At Depot Service Parts ListStocked IPI Valve AssemblyCERONA-42 Fan Kit GFK-160A Junction Box 4021-013 Box Paint Kit CERONA-42IPI Valve Assembly Limited Lifetime Warranty Heat & GLO GAS Appliance Products Limited Lifetime WarrantyContact Information
Related manuals
Manual 62 pages 22.54 Kb Manual 1 pages 2.44 Kb