13 Finishing

A. Mantel and Wall Projections

WARNING! Risk of Fire! Comply with all minimum clear- ances as specified. Framing closer than the minimums list- ed must be constructed entirely of noncombustible materials (i.e., steel studs, concrete board, etc.).

Combustible Mantels

TO CEILING

Note: All

 

18

 

measurements

 

12

 

in inches.

 

 

 

11

 

 

 

 

 

 

10

32

 

 

9

 

 

 

 

8

25

 

 

7

19

 

 

6

 

 

18

 

 

5

 

 

17

 

 

4

16

 

 

3

 

 

15

 

 

 

 

 

 

14

 

 

 

13

 

2-1/2

12

 

 

11

 

 

 

 

 

 

10

 

 

 

5

 

 

 

MEASUREMENTS FROM

 

 

TOP EDGE OF THE OPENING

 

Note: Measurement is taken from top of the opening, NOT the top of the fireplace.

Figure 13.1 Minimum Vertical and Maximum Horizontal

Dimensions of Combustibles

Combustible Mantel Legs or Wall Projections

INTERIOR WALL

TOP VIEW

A

B

 

FIREPLACE OPENING

MANTEL LEG OR WALL PROJECTIONS

If A minimum is ____, then B maximum is_____.

A

Inches

2-7/16

3-7/16

4-7/16

5-7/16

6-7/16

7-7/16

Millimeters

62

87

113

138

164

189

 

B

Inches

1

2

3

4

5

Millimeters

25

51

76

102

127

Figure 13.2 Combustible Mantel Leg or Wall Projections (Acceptable on both sides of opening)

B. Facing Material

Metal front faces may be covered with non-combustible materials only.

Facing and/or finishing materials must not interfere with air flow through louvers, operation of louvers or doors, or access for service.

Facing and/or finishing materials must never overhang into the glass opening.

Observe all clearances when applying combustible materials.

Seal joints between the finished wall and appliance top and sides using a 300 ºF minimum sealant. Refer to Figure 13.3.

WARNING! Risk of Fire! DO NOT apply combustible materials beyond the minimum clearances. Comply with all minimum clearances to combustibles as specified in this manual. Overlapping materials could ignite and will interfere with proper operation of doors and louvers.

NON-COMBUSTIBLE ZONE (Shaded areas)

41 in.

39-3/8 in.

1 in.

1 in.

Figure 13.3 Noncombustible Facing Diagram

Heat & Glo • BE-41C / LP, BE-41IPIC / LP • 2105-900 Rev. P • 6/09

51

Image 51
Contents Hot glass will cause burns What to do if you smell gasHomeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalFinal inspection by Turn off all electric power to the applianceOn position. The ON/OFF switch may Lighting Instructions IPILighting Instructions Standing Pilot For Your Safety Read Before Lighting Lighting InstructionsAfter Fireplace is Lit Frequently Asked QuestionsRemote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingEither cobrahead or SIT Typical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseMantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyV1 Minimum H1 Maximum Vent Diagrams Top Vent Horizontal TerminationOne Elbow Two ElbowsMin Max Top Vent Horizontal Termination Three ElbowsBreak Here Maximum + V 2 Min Top Vent Vertical TerminationH1 + H2 V1 + V2 Minimum H1 + H2 Maximum Top Vent Vertical Termination Three ElbowsHeat & Glo BE-41C / LP, BE-41IPIC / LP 2105-900 Rev. P 6/09 Rear Vent Horizontal Termination Two Elbows H1 Maximum V1 Minimum H1 + H2 MaximumH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max H1 + H2 Maximum V1 Minimum Rear Vent Vertical Termination One ElbowV1 Minimum H1 + H2 + H3 Rear Vent Vertical Termination Three ElbowsCombustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP SLP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear VentSecuring and Leveling the Appliance Installing the Non-combustible BoardAssemble Pipe Sections Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Vent Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Decorative Wall Components SLP onlyHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap DVP and SLP Pipe Ansi Z223.1 and CAN/CGA-B149 installation codesRefer to of this manual Gas Connection Gas InformationFuel Conversion Gas PressureOptional Accessories Requirements Wiring RequirementsIntelliFire Ignition System Wiring Standing Pilot Ignition System WiringIntelliFire Pilot Ignition IPI Wiring Diagram Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingFinish Door FIT Material See Maximum Thickness DoorsAppliance Setup Install the Log Assembly LOG Assembly LOGS-6000BELog Placement Tabs Burner Install Trim and/or SurroundAir Shutter Setting Air Shutter SettingsTroubleshooting Symptom Possible Causes Corrective ActionStanding Pilot Ignition System Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters DVP vent components Vent Components DiagramsDVP vent components Horizontal Termination Cap13-3/4 13-7/8 352 mm 349 mm 787 mm 13-1/4 367 mm 24-5/8 625 mm 27-1/2 127 mmRoof Flashing Multi-pak 13-3/4 11-7/8 349 mm 302 mmDVP-TVHW DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP 2 in mm 152 mm 8 in mm 251 mm SLP-90ST 90 Elbow 165 mm 222 mm 168 mmElbow Effective Height Length Horizontal Pipe SupportCeiling Firestop Cathedral CeilingSnorkel Support Box-Black Termination CapContact Information