10 Installing Vent Pipe (DVP and SLP Pipe)

A. Assemble Vent Sections (DVP Pipe Only)

Attach Vent to the Firebox Assembly

Note: The end of the pipe sections with the lanced tabs will face toward the appliance.

Attach the first pipe section to the starting collar:

Lanced pipe end to the starting collar

Inner pipe over inner collar

Push the pipe section until all lanced tabs snap in place

Lightly tug on pipe to confirm it has locked.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

All outer pipe joints must be sealed with high temperature silicone, including the slip section that connects directly to the horizontal termination cap.

Figure 10.1 High Temperature Silicone Sealant

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 10.1

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when remov- ing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

Assemble Pipe Sections

A

B

Figure 10.2

Lances

Figure 10.3

Per Figure 10.2:

Start the inner pipe on the lanced end of section A into the flared end of section B.

Start the outer pipe of section A over the outer pipe of section B.

Once both vents sections are started, push firmly until all lanced tabs lock into place.

Lightly tug on the pipe to confirm the tabs have locked.

It is acceptable to use screws no longer than 1/2 in. (13

mm)to hold outer pipe sections together. If predrilling holes, DO NOT penetrate inner pipe.

For 90º and 45º elbows that are changing the vent direction from horizontal to vertical, one screw minimum should be put in the outer flue at the horizontal elbow joint to prevent the elbow from rotating. Use screws no longer than 1/2 in. (13 mm). If predrilling screw holes, DO NOT penetrate inner pipe.

Note: Make sure that the seams are not aligned to prevent unintentional disconnection.

CORRECT

Figure 10.4 Seams

INCORRECT

40

Heat & Glo • BE-41C / LP, BE-41IPIC / LP • 2105-900 Rev. P • 6/09

Image 40
Contents What to do if you smell gas Hot glass will cause burnsCongratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceTurn off all electric power to the appliance On position. The ON/OFF switch mayLighting Instructions IPI Final inspection byFor Your Safety Read Before Lighting Lighting Instructions Lighting Instructions Standing PilotFrequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsEither cobrahead or SIT Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesCombustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsVent Diagrams Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 MaximumTop Vent Horizontal Termination Three Elbows Min MaxBreak Here Top Vent Vertical Termination Maximum + V 2 MinTop Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumHeat & Glo BE-41C / LP, BE-41IPIC / LP 2105-900 Rev. P 6/09 H1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Rear Vent Vertical Termination One Elbow H1 + H2 Maximum V1 MinimumRear Vent Vertical Termination Three Elbows V1 Minimum H1 + H2 + H3Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outInstalling the Non-combustible Board Securing and Leveling the ApplianceInstalling Vent Pipe DVP and SLP Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Ansi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination Cap DVP and SLP PipeRefer to of this manual Gas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements IntelliFire Ignition System WiringStanding Pilot Ignition System Wiring Optional Accessories RequirementsElectrical Service and Repair IntelliFire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialDoors Finish Door FIT Material See Maximum ThicknessAppliance Setup LOG Assembly LOGS-6000BE Install the Log AssemblyLog Placement Tabs Install Trim and/or Surround Air Shutter SettingAir Shutter Settings BurnerSymptom Possible Causes Corrective Action TroubleshootingStanding Pilot Ignition System Troubleshooting Symptom Possible Cause Corrective ActionIntelliFire Ignition System Ues to spark, and main Reference Materials Appliance Dimension DiagramLocation Inches Millimeters Vent Components Diagrams DVP vent componentsHorizontal Termination Cap DVP vent components787 mm 13-1/4 367 mm 24-5/8 625 mm 27-1/2 127 mm Roof Flashing Multi-pak 13-3/4 11-7/8 349 mm302 mm 13-3/4 13-7/8 352 mm 349 mmDVP-TVHW DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP 165 mm 222 mm 168 mm Elbow Effective Height LengthHorizontal Pipe Support 2 in mm 152 mm 8 in mm 251 mm SLP-90ST 90 ElbowCathedral Ceiling SnorkelSupport Box-Black Termination Cap Ceiling FirestopContact Information