Heat & Glo LifeStyle BE-41C, BE-41IPIC Requirements for the Commonwealth of Massachusetts

Page 8

Note: The following requirements reference various Massachusetts and national codes not contained in this document.

H.Requirements for the Commonwealth of Massachusetts

For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or structure used in whole or in part for residential purposes, including those owned or operated by the Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above finished grade in the area of the venting, in- cluding but not limited to decks and porches, the following requirements shall be satisfied:

Installation of Carbon Monoxide Detectors

At the time of installation of the side wall horizontal vented gas fueled equipment, the installing plumber or gas fitter shall observe that a hard wired carbon monoxide detector with an alarm and battery back-up is installed on the floor level where the gas equipment is to be installed. In addi- tion, the installing plumber or gas fitter shall observe that a battery operated or hard wired carbon monoxide detec- tor with an alarm is installed on each additional level of the dwelling, building or structure served by the side wall horizontal vented gas fueled equipment. It shall be the responsibility of the property owner to secure the services of qualified licensed professionals for the installation of hard wired carbon monoxide detectors.

In the event that the side wall horizontally vented gas fu- eled equipment is installed in a crawl space or an attic, the hard wired carbon monoxide detector with alarm and battery back-up may be installed on the next adjacent floor level.

In the event that the requirements of this subdivision can not be met at the time of completion of installation, the owner shall have a period of thirty (30) days to comply with the above requirements; provided, however, that dur- ing said thirty (30) day period, a battery operated carbon monoxide detector with an alarm shall be installed.

Approved Carbon Monoxide Detectors

Each carbon monoxide detector as required in accor- dance with the above provisions shall comply with NFPA 720 and be ANSI/UL 2034 listed and IAS certified.

Signage

A metal or plastic identification plate shall be permanent- ly mounted to the exterior of the building at a minimum height of eight (8) feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fu- eled heating appliance or equipment. The sign shall read, in print size no less than one-half (1/2) in. in size, “GAS

VENT DIRECTLY BELOW. KEEP CLEAR OF ALL OB- STRUCTIONS”.

Inspection

The state or local gas inspector of the side wall horizon- tally vented gas fueled equipment shall not approve the installation unless, upon inspection, the inspector ob- serves carbon monoxide detectors and signage installed in accordance with the provisions of 248 CMR 5.08(2)(a)1 through 4.

Exemptions

The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4:

The equipment listed in Chapter 10 entitled “Equipment Not Required To Be Vented” in the most current edition of NFPA 54 as adopted by the Board; and

Product Approved side wall horizontally vented gas fu- eled equipment installed in a room or structure separate from the dwelling, building or structure used in whole or in part for residential purposes.

MANUFACTURER REQUIREMENTS

Gas Equipment Venting System Provided

When the manufacturer of Product Approved side wall horizontally vented gas equipment provides a venting system design or venting system components with the equipment, the instructions provided by the manufacturer for installation of the equipment and the venting system shall include:

Detailed instructions for the installation of the venting system design or the venting system components; and

A complete parts list for the venting system design or venting system.

Gas Equipment Venting System NOT Provided

When the manufacturer of a Product Approved side wall horizontally vented gas fueled equipment does not pro- vide the parts for venting the flue gases, but identifies “special venting systems”, the following requirements shall be satisfied by the manufacturer:

The referenced “special venting system” instructions shall be included with the appliance or equipment in- stallation instructions; and

The “special venting systems” shall be Product Ap- proved by the Board, and the instructions for that sys- tem shall include a parts list and detailed installation instructions.

A copy of all installation instructions for all Product Ap- proved side wall horizontally vented gas fueled equip- ment, all venting instructions, all parts lists for venting instructions, and/or all venting design instructions shall remain with the appliance or equipment at the completion of the installation.

See Gas Connection section for additional Common- wealth of Massachusetts requirements.

8

Heat & Glo • BE-41C / LP, BE-41IPIC / LP • 2105-900 Rev. P • 6/09

Image 8
Contents What to do if you smell gas Hot glass will cause burnsCongratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceTurn off all electric power to the appliance On position. The ON/OFF switch mayLighting Instructions IPI Final inspection byFor Your Safety Read Before Lighting Lighting Instructions Lighting Instructions Standing PilotFrequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsEither cobrahead or SIT Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesCombustible Mantel Legs or Wall Projections Mantel and Wall ProjectionsCombustible Mantels Termination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsVent Diagrams Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 MaximumTop Vent Horizontal Termination Three Elbows Min MaxBreak Here Top Vent Vertical Termination Maximum + V 2 MinTop Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumHeat & Glo BE-41C / LP, BE-41IPIC / LP 2105-900 Rev. P 6/09 H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Vertical Termination One Elbow H1 + H2 Maximum V1 MinimumRear Vent Vertical Termination Three Elbows V1 Minimum H1 + H2 + H3Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outInstalling the Non-combustible Board Securing and Leveling the ApplianceInstalling Vent Pipe DVP and SLP Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Refer to of this manual Install Horizontal Termination Cap DVP and SLP PipeAnsi Z223.1 and CAN/CGA-B149 installation codes Gas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements IntelliFire Ignition System WiringStanding Pilot Ignition System Wiring Optional Accessories RequirementsElectrical Service and Repair IntelliFire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialDoors Finish Door FIT Material See Maximum ThicknessAppliance Setup LOG Assembly LOGS-6000BE Install the Log AssemblyLog Placement Tabs Install Trim and/or Surround Air Shutter SettingAir Shutter Settings BurnerStanding Pilot Ignition System TroubleshootingSymptom Possible Causes Corrective Action Troubleshooting Symptom Possible Cause Corrective ActionIntelliFire Ignition System Ues to spark, and main Location Inches Millimeters Appliance Dimension DiagramReference Materials Vent Components Diagrams DVP vent componentsHorizontal Termination Cap DVP vent components787 mm 13-1/4 367 mm 24-5/8 625 mm 27-1/2 127 mm Roof Flashing Multi-pak 13-3/4 11-7/8 349 mm302 mm 13-3/4 13-7/8 352 mm 349 mmDVP-TVHW DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP 165 mm 222 mm 168 mm Elbow Effective Height LengthHorizontal Pipe Support 2 in mm 152 mm 8 in mm 251 mm SLP-90ST 90 ElbowCathedral Ceiling SnorkelSupport Box-Black Termination Cap Ceiling FirestopContact Information