Heat & Glo LifeStyle ST-36TRB-IPI Wall Penetration Framing, Combustible Wall Penetration, Correct

Page 37

CORRECT

COMBUSTIBLE SURFACE

INCORRECT

 

 

DIRECTION

 

 

UP

 

 

HEAT SHIELD

 

 

90º ELBOW

 

Figure 8.3

 

 

If the combustible materials are not in place at the time of install the elbow heat shield may be screwed to the exhaust pipe (see Figure 8.4). Cut the tabs as shown and bend down. Secure the heat shield to the pipe maintaining 3 inch to 4 inch between the pipe and shield.

SCREW

3 in.

(76 mm)

Figure 8.4

C. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield firestop must be placed on each side of an interior wall. A minimum 1-1/2 in. (38 mm) overlap of attached heat shields must be maintained.

DVP pipe - A wall shield firestop is required on one side only on interior walls. If your local inspector requires a wall shield firestop on both sides, then both wall shield firestops must have a heat shield (refer to Section 16.B) attached to them.

See Section 10.M for information for regarding the in- stallation of a horizontal termination cap.

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncom- bustible materials such as concrete, a hole with diameter one inch greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

10 in.

12 in.

C

 

 

 

 

D

10 in.

12 in.

 

A* B*

A*

B*

C

D

43-3/4 in.

28 in.

42-3/4 in.

27 in.

*Shows center of vent framing hole for top or rear venting. The center of the hole is one (1) inch (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.5 Wall Penetration

Note: When terminating horizontally off the top of the unit using SLP pipe, a 10 in. x 10 in. framing hole is required.

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

37

Image 37
Contents HOT Surfaces What to do if you smell gasHot glass will cause burns Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fixed Glass Assembly Blower InstallationRemote Controls, Wall Controls and Wall Switches Blower Kit optionalFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseRCOR-36TRB-IPI PIER/LCOR/RCOR Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelSee-Through Non-Combustible Mantel PIER/LCOR/RCOR Non-Combustible MantelTOP View Vent Termination Minimum Clearances Termination LocationsGas, Wood or Fuel Oil Termination Cap Covered Alcove Applications Approved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsTo SLP series vent pipe, if desired Vent DiagramsTop Vent-Horizontal Termination-Two 45 Elbows Elbow on rear vent appliancesTwo Elbows Top Vent Horizontal Termination One ElbowV1 Minimum H1 Maximum V1 Minimum H1 + H2 Maximum152 mm Top Vent Horizontal Termination Three Elbows305 mm Exhaust restrictor Instructions 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft Break HereMaximum + V 2 Minimum Two Elbows Three Elbows12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m Maximum H1+ H2 V1 + V2 Minimum H1+ H2 MaximumPage H1 Maximum V1 Minimum H2 Maximum H1+ H2 Maximum Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 V1 Minimum H1 Maximum Rear Vent Vertical Termination One ElbowV1+ H1 = 40 ft 12.2 m Maximum Minimum + H 2 MaximumH1 Maximum V1 Minimum H1+ H2 Maximum Rear Vent Vertical Termination Three ElbowsV1 Minimum H1+ H2+ H3 Maximum Pipe Clearances to Combustibles Vent Clearances and FramingContinue Adding Vent Components Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration CorrectPipe DVP SLP Vertical Penetration FramingFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Top Vent Appliance PreparationProceed to . C Cut the metal retaining band Rear VentAttach Nailing Tab to Front Corner of Unit Securing and Leveling the ApplianceAttach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Important Notice Heat shields may not be field constructedDVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionOptional Accessories Requirements Wiring RequirementsElectrical Information Intellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Optional Junction Box InstallationFinishing To install the Splatter GuardSplatter Guard To Remove the Splatter Guard To Close the Lower Access PanelPIER/LCOR/RCOR Mantel Projection Mantel and Wall Projections See-Through Mantel ProjectionFinishing Material Facing MaterialStop finishing material flush with opening Finishing material between 1 and 2 inches thick Finishing materials over 1 inch thickElevated Hearth Systems Appliance Setup 2128-935 Install the Log AssemblyIndentations Air Shutter Setting Install Trim Kits and SurroundsAir Shutter Settings Symptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System flame rectification has Reference Materials Appliance Dimension DiagramLocation Inches Millimeters Pier Dimensions Electrical Access GAS Line Left View Front View Right View40-1/2 Left View Front View Electrical Access GAS Line Right View24-1/2 33-1/2DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDDVP-TV Power Vent Inline Optional Wire HarnessPVI-SLP SLP-LPCCeiling Firestop ElbowSupport SLP-WSDVP-FBHT SLP-SNKD SLP-CCS-BKSLP-DCF-BK Log Set Assembly Service PartsAt Depot See Through Direct Vent Gas FireplacePier Direct Vent Fireplace PIER-36TRB-IPILeft Corner Direct Vent Fireplace LCOR-36TRB-IPIRight Corner Direct Vent Fireplace RCOR-36TRB-IPIStocked #15 Valve AssemblyLPK-DXV Service Parts ListContact Information