G. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.15

H. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris.

Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.18).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

47

Image 47
Contents Hot glass will cause burns What to do if you smell gasHOT Surfaces Homeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Blower Kit optional Blower InstallationFixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseRCOR-36TRB-IPI PIER/LCOR/RCOR Non-Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelPIER/LCOR/RCOR Combustible Mantel See-Through Non-Combustible MantelTOP View Gas, Wood or Fuel Oil Termination Cap Termination LocationsVent Termination Minimum Clearances Covered Alcove Applications Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyElbow on rear vent appliances Vent DiagramsTo SLP series vent pipe, if desired Top Vent-Horizontal Termination-Two 45 ElbowsV1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 Maximum305 mm Top Vent Horizontal Termination Three Elbows152 mm Exhaust restrictor Instructions 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft Break HereH1+ H2 V1 + V2 Minimum H1+ H2 Maximum Two Elbows Three ElbowsMaximum + V 2 Minimum 12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m MaximumPage H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2 Maximum H1+ H2 Maximum Minimum + H 2 Maximum Rear Vent Vertical Termination One ElbowV1 Minimum H1 Maximum V1+ H1 = 40 ft 12.2 m MaximumV1 Minimum H1+ H2+ H3 Maximum Rear Vent Vertical Termination Three ElbowsH1 Maximum V1 Minimum H1+ H2 Maximum Continue Adding Vent Components Vent Clearances and FramingPipe Clearances to Combustibles Correct Wall Penetration FramingCombustible Wall Penetration Non-Combustible Wall PenetrationPipe DVP SLP Vertical Penetration FramingVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Proceed to . C Appliance PreparationTop Vent Cut the metal retaining band Rear VentAttach Nailing Tab to Front Corner of Unit Securing and Leveling the ApplianceAssemble Pipe Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Vent Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingImportant Notice Heat shields may not be field constructed Install Vertical Termination CapInstall Decorative Wall Components SLP only Heat Shield Requirements for Horizontal TerminationDVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsOptional Accessories Requirements Intellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Optional Junction Box InstallationSplatter Guard To install the Splatter GuardFinishing To Remove the Splatter Guard To Close the Lower Access PanelPIER/LCOR/RCOR Mantel Projection Mantel and Wall Projections See-Through Mantel ProjectionStop finishing material flush with opening Facing MaterialFinishing Material Finishing material between 1 and 2 inches thick Finishing materials over 1 inch thickElevated Hearth Systems Appliance Setup 2128-935 Install the Log AssemblyIndentations Air Shutter Settings Install Trim Kits and SurroundsAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action flame rectification has Location Inches Millimeters Appliance Dimension DiagramReference Materials Pier Dimensions Electrical Access GAS Line Left View Front View Right View33-1/2 Left View Front View Electrical Access GAS Line Right View40-1/2 24-1/2DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFLDVP-TV SLP-LPC Optional Wire HarnessPower Vent Inline PVI-SLPSLP-WS ElbowCeiling Firestop SupportSLP-DCF-BK SLP-SNKD SLP-CCS-BKDVP-FBHT See Through Direct Vent Gas Fireplace Service PartsLog Set Assembly At DepotPier Direct Vent Fireplace PIER-36TRB-IPILeft Corner Direct Vent Fireplace LCOR-36TRB-IPIRight Corner Direct Vent Fireplace RCOR-36TRB-IPIStocked #15 Valve AssemblyLPK-DXV Service Parts ListContact Information