Heat & Glo LifeStyle ST-36TRB-IPI owner manual flame rectification has

Page 65

Intellifire Ignition System - (continued)

Symptom

Possible Cause

Corrective Action

 

 

 

 

 

 

 

a. A shorted or loose connection in flame

Verify all connections to wiring diagram in manual. Verify

 

4. Pilot lights but contin-

sensing rod.

connections underneath pilot assembly are tight. Verify

 

ues to spark, and main

 

connections are not grounding out to metal chassis, pilot

 

burner will not ignite.

 

burner, pilot enclosure or screen if present, or any other

 

(If the pilot continues

 

metal object.

 

 

to spark after the

 

 

 

 

b. Poor flame rectification or contaminated

With fixed glass assembly in place, verify that

flame is

 

pilot flame has been lit,

 

flame sensing rod.

engulfing flame sensing rod on left side of pilot hood. Flame

 

flame rectification has

 

 

sensing rod should glow shortly after ignition. Verify correct

 

not occurred.)

 

 

 

pilot orifice is installed and gas inlet is set to

pressure

 

 

 

 

 

specifications. Polish flame-sensing rod with fine steel wool

 

 

 

 

 

to remove any contaminants that may have accumulated on

 

 

 

flame sensing rod.

 

 

 

 

 

 

 

c. Module is not grounded.

Verify module is securely grounded to metal chassis of

 

 

 

appliance. Verify that wire harness is firmly connected to

 

 

 

the module.

 

 

 

 

 

 

 

d. Damaged pilot assembly or contami-

Verify that ceramic insulator around the flame sensing

 

 

nated flame sensing rod.

rod is not cracked, damaged, or loose. Verify connection

 

 

from flame sensing rod to white sensor wire. Polish flame-

 

 

sensing rod with fine steel wool to remove any contaminants

 

 

 

that may have accumulated on flame sensing rod. Verify

 

 

 

continuity with a multimeter with ohms set at lowest range.

 

 

 

Replace pilot if any damage is detected.

 

 

 

 

 

 

 

e. Module.

Turn ON/OFF rocker switch or wall switch to OFF position.

 

 

 

Remove ignitor wire “I” from module. Place ON/OFF rocker

 

 

 

switch or wall switch in ON position. If there is no spark at

 

 

 

“I” terminal module must be replaced. If there is a spark at

 

 

 

“I” terminal, module is fine.

 

 

 

 

 

 

 

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

65

Image 65
Contents Hot glass will cause burns What to do if you smell gasHOT Surfaces Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Fixed Glass Assembly Blower InstallationRemote Controls, Wall Controls and Wall Switches Blower Kit optionalFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseRCOR-36TRB-IPI PIER/LCOR/RCOR Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelSee-Through Non-Combustible Mantel PIER/LCOR/RCOR Non-Combustible MantelTOP View Gas, Wood or Fuel Oil Termination Cap Termination LocationsVent Termination Minimum Clearances Covered Alcove Applications Approved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsTo SLP series vent pipe, if desired Vent DiagramsTop Vent-Horizontal Termination-Two 45 Elbows Elbow on rear vent appliancesTwo Elbows Top Vent Horizontal Termination One ElbowV1 Minimum H1 Maximum V1 Minimum H1 + H2 Maximum305 mm Top Vent Horizontal Termination Three Elbows152 mm Exhaust restrictor Instructions 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft Break HereMaximum + V 2 Minimum Two Elbows Three Elbows12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m Maximum H1+ H2 V1 + V2 Minimum H1+ H2 MaximumPage H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2 Maximum H1+ H2 Maximum V1 Minimum H1 Maximum Rear Vent Vertical Termination One ElbowV1+ H1 = 40 ft 12.2 m Maximum Minimum + H 2 MaximumV1 Minimum H1+ H2+ H3 Maximum Rear Vent Vertical Termination Three ElbowsH1 Maximum V1 Minimum H1+ H2 Maximum Continue Adding Vent Components Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration CorrectPipe DVP SLP Vertical Penetration FramingVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Proceed to . C Appliance PreparationTop Vent Cut the metal retaining band Rear VentAttach Nailing Tab to Front Corner of Unit Securing and Leveling the ApplianceAttach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Important Notice Heat shields may not be field constructedDVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionElectrical Information Wiring RequirementsOptional Accessories Requirements Intellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Optional Junction Box InstallationSplatter Guard To install the Splatter GuardFinishing To Remove the Splatter Guard To Close the Lower Access PanelPIER/LCOR/RCOR Mantel Projection Mantel and Wall Projections See-Through Mantel ProjectionStop finishing material flush with opening Facing MaterialFinishing Material Finishing material between 1 and 2 inches thick Finishing materials over 1 inch thickElevated Hearth Systems Appliance Setup 2128-935 Install the Log AssemblyIndentations Air Shutter Settings Install Trim Kits and SurroundsAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action flame rectification has Location Inches Millimeters Appliance Dimension DiagramReference Materials Pier Dimensions Electrical Access GAS Line Left View Front View Right View40-1/2 Left View Front View Electrical Access GAS Line Right View24-1/2 33-1/2DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDDVP-TV Power Vent Inline Optional Wire HarnessPVI-SLP SLP-LPCCeiling Firestop ElbowSupport SLP-WSSLP-DCF-BK SLP-SNKD SLP-CCS-BKDVP-FBHT Log Set Assembly Service PartsAt Depot See Through Direct Vent Gas FireplacePier Direct Vent Fireplace PIER-36TRB-IPILeft Corner Direct Vent Fireplace LCOR-36TRB-IPIRight Corner Direct Vent Fireplace RCOR-36TRB-IPIStocked #15 Valve AssemblyLPK-DXV Service Parts ListContact Information