6 Termination Locations

A. Vent Termination Minimum Clearances

WARNING

Fire Risk.

Maintain vent clearance to combustibles as specified.

DO NOT pack air space with insulation or other materials.

Failure to keep insulation or other materials away from vent pipe may cause overheating and fire.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12...........................................................1.0*

Over 6/12 to 7/12.................................................1.25*

Over 7/12 to 8/12.................................................1.5*

Over 8/12 to 9/12.................................................2.0*

Over 9/12 to 10/12...............................................2.5

Over 10/12 to 11/12 .............................................3.25

Over 11/12 to 12/12 .............................................4.0

Over 12/12 to 14/12.............................................5.0

Over 14/12 to 16/12.............................................6.0

Over 16/12 to 18/12.............................................7.0

Over 18/12 to 20/12.............................................7.5

Over 20/12 to 21/12.............................................8.0

* 3 foot minimum in snow regions

Figure 6.1 Minimum Height From Roof To Lowest Discharge

Opening

 

 

A

B

6 in. (minimum) up to 20 in.

18 in. minimum

152 mm/508 mm

457 mm

20 in. and over

0 in. minimum

Gas, Wood or Fuel Oil

Termination Cap

B

A *

Gas

Termination

Cap **

*If using decorative cap cover(s), this distance may need to be increased. Refer to the installation instructions supplied with the decorative cap cover.

**In a staggered installation with both gas and wood or fuel oil terminations, the wood or fuel oil termination cap must be higher than the gas termination cap.

Figure 6.2 Staggered Termination Caps

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

23

Image 23
Contents Hot glass will cause burns What to do if you smell gasHOT Surfaces Homeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Blower Kit optional Blower InstallationFixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseRCOR-36TRB-IPI PIER/LCOR/RCOR Non-Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelPIER/LCOR/RCOR Combustible Mantel See-Through Non-Combustible MantelTOP View Gas, Wood or Fuel Oil Termination Cap Termination LocationsVent Termination Minimum Clearances Covered Alcove Applications Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyElbow on rear vent appliances Vent DiagramsTo SLP series vent pipe, if desired Top Vent-Horizontal Termination-Two 45 ElbowsV1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 Maximum305 mm Top Vent Horizontal Termination Three Elbows152 mm Exhaust restrictor Instructions 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft Break HereH1+ H2 V1 + V2 Minimum H1+ H2 Maximum Two Elbows Three ElbowsMaximum + V 2 Minimum 12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m MaximumPage H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2 Maximum H1+ H2 Maximum Minimum + H 2 Maximum Rear Vent Vertical Termination One ElbowV1 Minimum H1 Maximum V1+ H1 = 40 ft 12.2 m MaximumV1 Minimum H1+ H2+ H3 Maximum Rear Vent Vertical Termination Three ElbowsH1 Maximum V1 Minimum H1+ H2 Maximum Continue Adding Vent Components Vent Clearances and FramingPipe Clearances to Combustibles Correct Wall Penetration FramingCombustible Wall Penetration Non-Combustible Wall PenetrationPipe DVP SLP Vertical Penetration FramingVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Proceed to . C Appliance PreparationTop Vent Cut the metal retaining band Rear VentAttach Nailing Tab to Front Corner of Unit Securing and Leveling the ApplianceAssemble Pipe Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Vent Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingImportant Notice Heat shields may not be field constructed Install Vertical Termination CapInstall Decorative Wall Components SLP only Heat Shield Requirements for Horizontal TerminationDVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsOptional Accessories Requirements Intellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Optional Junction Box InstallationSplatter Guard To install the Splatter GuardFinishing To Remove the Splatter Guard To Close the Lower Access PanelPIER/LCOR/RCOR Mantel Projection Mantel and Wall Projections See-Through Mantel ProjectionStop finishing material flush with opening Facing MaterialFinishing Material Finishing material between 1 and 2 inches thick Finishing materials over 1 inch thickElevated Hearth Systems Appliance Setup 2128-935 Install the Log AssemblyIndentations Air Shutter Settings Install Trim Kits and SurroundsAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action flame rectification has Location Inches Millimeters Appliance Dimension DiagramReference Materials Pier Dimensions Electrical Access GAS Line Left View Front View Right View33-1/2 Left View Front View Electrical Access GAS Line Right View40-1/2 24-1/2DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFLDVP-TV SLP-LPC Optional Wire HarnessPower Vent Inline PVI-SLPSLP-WS ElbowCeiling Firestop SupportSLP-DCF-BK SLP-SNKD SLP-CCS-BKDVP-FBHT See Through Direct Vent Gas Fireplace Service PartsLog Set Assembly At DepotPier Direct Vent Fireplace PIER-36TRB-IPILeft Corner Direct Vent Fireplace LCOR-36TRB-IPIRight Corner Direct Vent Fireplace RCOR-36TRB-IPIStocked #15 Valve AssemblyLPK-DXV Service Parts ListContact Information