D. Vertical Penetration Framing

A ceiling firestop MUST be used between floors and attics.

DVP pipe only - Frame an opening 10 in. by 10 in. (254 mm by 254 mm) whenever the vent penetrates a ceiling/floor (see Figure 8.6).

SLP pipe only - Frame opening 9 in. x 9 in. (229 mm x 229 mm) whenever the vent penetrates a ceiling/floor (see Figure 8.6).

Frame the area with the same sized lumber as used in ceiling/floor joist.

The ceiling firestop may be installed above or below the ceiling joists when installed with a attic insulation shield. It must be under joists between floors that are not insulated. Refer to Figure 8.7.

Secure with three fasteners on each side.

WARNING! Risk of Fire! DO NOT pack insu- lation around the vent. Insulation must be kept back from the pipe to prevent overheating.

 

ATTIC ABOVE

 

A

 

A

PIPE

A

DVP

10 in. (254 mm)

SLP

9 in. (229 mm)

Figure 8.6

 

 

INSTALL ATTIC INSULATION SHIELDS

 

BEFORE OR AFTER INSTALLATION OF VENT SYSTEM

 

3 FASTENERS

 

 

PER SIDE

 

CEILING FIRESTOP

CEILING FIRESTOP

INSTALLED BELOW CEILING

INSTALLED ABOVE CEILING

Figure 8.7

Installing the Attic Shield

 

38

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

Image 38
Contents Hot glass will cause burns What to do if you smell gasHOT Surfaces Congratulations Homeowner Reference InformationTable of Contents User GuideFinishing Appliance SetupTroubleshooting Reference Materials B. Limited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Remote Controls, Wall Controls and Wall Switches Blower InstallationFixed Glass Assembly Blower Kit optionalWhat to do if YOU Smell GAS Lighting Instructions IPIFinal inspection by GAS ValveAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Glass Cleaning Maintenance and ServiceMaintenance Tasks-Homeowner Remote ControlVenting Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsBurner Ignition and Operation IPI Pilot Flame PatternsGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesRCOR-36TRB-IPI See-Through Non-Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelPIER/LCOR/RCOR Combustible Mantel PIER/LCOR/RCOR Non-Combustible MantelTOP View Gas, Wood or Fuel Oil Termination Cap Termination LocationsVent Termination Minimum Clearances Covered Alcove Applications Vent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsTop Vent-Horizontal Termination-Two 45 Elbows Vent DiagramsTo SLP series vent pipe, if desired Elbow on rear vent appliancesV1 Minimum H1 Maximum Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 + H2 Maximum305 mm Top Vent Horizontal Termination Three Elbows152 mm Exhaust restrictor Instructions Break Here 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m Maximum Two Elbows Three ElbowsMaximum + V 2 Minimum H1+ H2 V1 + V2 Minimum H1+ H2 MaximumPage H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2 Maximum H1+ H2 Maximum V1+ H1 = 40 ft 12.2 m Maximum Rear Vent Vertical Termination One ElbowV1 Minimum H1 Maximum Minimum + H 2 MaximumV1 Minimum H1+ H2+ H3 Maximum Rear Vent Vertical Termination Three ElbowsH1 Maximum V1 Minimum H1+ H2 Maximum Continue Adding Vent Components Vent Clearances and FramingPipe Clearances to Combustibles Non-Combustible Wall Penetration Wall Penetration FramingCombustible Wall Penetration CorrectVertical Penetration Framing Pipe DVP SLPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Proceed to . C Appliance PreparationTop Vent Rear Vent Cut the metal retaining bandSecuring and Leveling the Appliance Attach Nailing Tab to Front Corner of UnitAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe Sections DVP Pipe OnlyAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Important Notice Heat shields may not be field constructedInstall Horizontal Termination Cap DVP and SLP Pipe DVP-HPC1 DVP-HPC2Gas Pressure Gas InformationFuel Conversion Gas ConnectionElectrical Information Wiring RequirementsOptional Accessories Requirements Intellifire Ignition Wiring Diagram with Remote Receiver Junction Box Installation Wall Switch Installation for Fan OptionalSplatter Guard To install the Splatter GuardFinishing To Close the Lower Access Panel To Remove the Splatter GuardMantel and Wall Projections See-Through Mantel Projection PIER/LCOR/RCOR Mantel ProjectionStop finishing material flush with opening Facing MaterialFinishing Material Finishing materials over 1 inch thick Finishing material between 1 and 2 inches thickElevated Hearth Systems Appliance Setup Install the Log Assembly 2128-935Indentations Air Shutter Settings Install Trim Kits and SurroundsAir Shutter Setting Intellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action flame rectification has Location Inches Millimeters Appliance Dimension DiagramReference Materials Electrical Access GAS Line Left View Front View Right View Pier Dimensions24-1/2 Left View Front View Electrical Access GAS Line Right View40-1/2 33-1/2Vent Components Diagrams DVP-AS2DVP-TRAP Horizontal Termination CapDVP-TRAPFL RF6M RF12MBEK DVP-BEK2 COOL-ADDDVP-TV PVI-SLP Optional Wire HarnessPower Vent Inline SLP-LPCSupport ElbowCeiling Firestop SLP-WSSLP-DCF-BK SLP-SNKD SLP-CCS-BKDVP-FBHT At Depot Service PartsLog Set Assembly See Through Direct Vent Gas FireplacePIER-36TRB-IPI Pier Direct Vent FireplaceLCOR-36TRB-IPI Left Corner Direct Vent FireplaceRCOR-36TRB-IPI Right Corner Direct Vent Fireplace#15 Valve Assembly StockedService Parts List LPK-DXVContact Information