D. Secure the Vent Sections

Vertical runs of DVP pipe must be supported every 8 ft. (2.44 m) after the 25 ft. (7.62 m) maximum unsupported rise.

Vertical runs of SLP pipe must be supported every 8 ft. (2.44 m).

Horizontal sections must be supported every 5 feet (1.52 m).

Vent supports or plumbers strap (spaced 120º apart) may be used to support vent sections. See Figures 10.8 and 10.9.

Wall shield firestops may be used to provide horizontal support to vent sections.

SLP ceiling firestops have tabs that may be used to provide vertical support.

WARNING! Risk of Fire, Explosion or Asphyxiation! Improper support may allow vent to sag and separate. Use vent run supports and connect vent sections per in- stallation instructions. DO NOT allow vent to sag below connection point to appliance.

120º

Figure 10.8 Securing Vertical Pipe Sections

120º

Figure 10.9 Securing Horizontal Pipe Sections

E. Disassemble Vent Sections

Rotate either section (see Figure 10.10) so the seams on both pipe sections are aligned as shown in Figure 10.11.

Pull carefully to separate the pieces of pipe.

Figure 10.10 Rotate Seams for Disassembly

Figure 10.11 Align and Disassemble Vent Sections

Heat & Glo • ST-36TRB-IPI, PIER-36TRB-IPI, LCOR-36TRB-IPI, RCOR-36TRB-IPI2128-900 Rev. H • 8/11

45

Image 45
Contents What to do if you smell gas HOT SurfacesHot glass will cause burns Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Fixed Glass Assembly Blower InstallationRemote Controls, Wall Controls and Wall Switches Blower Kit optionalFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseRCOR-36TRB-IPI PIER/LCOR/RCOR Combustible Mantel Mantel and Wall Projections See-Through Combustible MantelSee-Through Non-Combustible Mantel PIER/LCOR/RCOR Non-Combustible MantelTOP View Termination Locations Vent Termination Minimum ClearancesGas, Wood or Fuel Oil Termination Cap Covered Alcove Applications Approved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsTo SLP series vent pipe, if desired Vent DiagramsTop Vent-Horizontal Termination-Two 45 Elbows Elbow on rear vent appliancesTwo Elbows Top Vent Horizontal Termination One ElbowV1 Minimum H1 Maximum V1 Minimum H1 + H2 MaximumTop Vent Horizontal Termination Three Elbows 152 mm305 mm Exhaust restrictor Instructions 15 ft 20 ft 25 ft 30 ft 35 ft 40 ft 45 ft 50 ft 55 ft Break HereMaximum + V 2 Minimum Two Elbows Three Elbows12 ft 18 ft V1 + V2 + H1 = 50 ft 15.2 m Maximum H1+ H2 V1 + V2 Minimum H1+ H2 MaximumPage Rear Vent Horizontal Termination Two Elbows H1 Maximum V1 Minimum H2 Maximum H1+ H2 MaximumH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 V1 Minimum H1 Maximum Rear Vent Vertical Termination One ElbowV1+ H1 = 40 ft 12.2 m Maximum Minimum + H 2 MaximumRear Vent Vertical Termination Three Elbows H1 Maximum V1 Minimum H1+ H2 MaximumV1 Minimum H1+ H2+ H3 Maximum Vent Clearances and Framing Pipe Clearances to CombustiblesContinue Adding Vent Components Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration CorrectPipe DVP SLP Vertical Penetration FramingInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Appliance Preparation Top VentProceed to . C Cut the metal retaining band Rear VentAttach Nailing Tab to Front Corner of Unit Securing and Leveling the ApplianceAttach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Important Notice Heat shields may not be field constructedDVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionWiring Requirements Optional Accessories RequirementsElectrical Information Intellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Optional Junction Box InstallationTo install the Splatter Guard FinishingSplatter Guard To Remove the Splatter Guard To Close the Lower Access PanelPIER/LCOR/RCOR Mantel Projection Mantel and Wall Projections See-Through Mantel ProjectionFacing Material Finishing MaterialStop finishing material flush with opening Finishing material between 1 and 2 inches thick Finishing materials over 1 inch thickElevated Hearth Systems Appliance Setup 2128-935 Install the Log AssemblyIndentations Install Trim Kits and Surrounds Air Shutter SettingAir Shutter Settings Troubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System flame rectification has Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters Pier Dimensions Electrical Access GAS Line Left View Front View Right View40-1/2 Left View Front View Electrical Access GAS Line Right View24-1/2 33-1/2DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDDVP-TV Power Vent Inline Optional Wire HarnessPVI-SLP SLP-LPCCeiling Firestop ElbowSupport SLP-WSSLP-SNKD SLP-CCS-BK DVP-FBHTSLP-DCF-BK Log Set Assembly Service PartsAt Depot See Through Direct Vent Gas FireplacePier Direct Vent Fireplace PIER-36TRB-IPILeft Corner Direct Vent Fireplace LCOR-36TRB-IPIRight Corner Direct Vent Fireplace RCOR-36TRB-IPIStocked #15 Valve AssemblyLPK-DXV Service Parts ListContact Information