INSTALLATION

1)Remove the screw from the vent hole cover (vent cover 'A') on top of the unit.

2)Take the connector collar and press and rotate it into the hole to cut through the insulation layer. Remove the collar and removeinsulationfromthecollar.Thescrews for the inner cover should be exposed.

3)Remove the screws from the inner cover (vent cover 'B') and slide it back under the insulation.

4)Extend fl ex vent and pull the insulation sleeves over the 8” (203mm) diameter fl ex vents. Leave a short section of fl ex vent exposed at each end. On one end insert the collar into the fl ex vent and use a clamp to hold the fl ex vent in place.

5)Use tin snips to cut slits into the rim of the connector collar. A minimum of four tabs will be required so cut the slits 1” (25mm) (i.e. 1” (25mm) wide tabs) apart around the perimeter of the collar.

6)Install the connecting collar into the top of the unit until the bead of the collar rests against the top of the inner top of the unit. Reach inside the upper louver opening and use pliers to bend the tabs (minimum 4) out on the connector collar. A hammer may be required to lightly tap the tabs and bend them so that they fit tightly against the bottom of the inner top. Pull the insulation sleeve down to the top of the unit. Repeat steps 1-6 for the second fl ex vent and collar assembly.

Flex Vent

7)Position the vent frames for the Discharge Grilles into the rough opening of the stud wall framing. Make sure to add two insulation strips behind the flanges of the frame prior to securing to wall. The frames will fi t between studs framed at 16” (406mm) on center. Use 4 nails or screws to mount the frame to the stud framing.

Insulation

StripsConnecting

Collar

Discharge

Flex

Vent

Vent Grille

Clamp

 

8)Insert the connecting collar into the other end of the 5 ft. (1.5m) fl ex vent and use an adjustable clamp to hold the vent in place. Cut tabs into the rim of the connector collar (a minimum of 4 tabs will be required). Push the collar through the 8” (203mm) hole in the mounting frame. Use pliers to bend out tabs (minimum 4) to secure the collar to the mounting frame.

9)Pull the insulation sleeve up the fl ex vent to the back of the mounting frame. The fl ex vent should now be connected to both the unit and the mounting frames securely. Repeat steps 1-8 for the second fl ex vent assembly.

10)Install the block-off plate to the unit. The block-off plate will cover the upper louver opening of the unit and force the fan air to circulate through the two 8” (203mm) diameter fl ex vents. Put high temperature sealant onto the block-off plate. Mount the block-off plate onto the front of the unit and cover the upper louver opening. Make sure that all exposed holes in the block-off plate are sealed with high temperature sealant.

NOTE:

Make sure the block-off plate is fl ush and fastened tightly to the Regency FP90 Fireplace.

11)The rough opening size for the Chase Vent Grille is 3” H x 10”W (76mm H x 254mm W).

WARNING:

A chase vent of 30 sq. inches (194 cm2) MUST be installed in all applications, otherwise serious overheating of the chase may result. Use the chase vent supplied with the FP90 unit only or any equivalent one with the same or less restriction of air

fl ow (for U.S. installations only).

12)Recheck all fl ex vent-work connections to make sure that they are secure. Install wall sheathingandcut-outopeningsforthechase ventilation, and hot air discharge outlets.

13)Install the Chase Vent Grille and install the Discharge Vent Grilles for the hot air outlets.

NOTE:

There must be a minimum of 5" (127mm) between the gravity air vents.

FINISHING THE

REGENCY FP90

Completing The Facing

Facing materials must be thin veneer (non-self supporting facades) or self supporting facades. If you are installing a thin veneer facade the RegencyMasonryRetainerKit isrecommended. All facades must be Non-Combustiblesuch as brick, rock or ceramic tile. See Clearance to Combustible diagram at the beginning of this manual to determine the extent to which you must use non-combustible materials. Gypsum wallboard is not non-combustible.

Non-self Supporting, Thin Veneer

Facades Installation

1)Install heavy expanded metal only on the top half of the fireplace using a drill to pre- drill holes and install using tap screws at locations as indicated on kit.

2)Install metal edging of kit on each side of the doors making sure the edges fi t nicely with the arch edge above.

3)Cover the rest of the area with wire mesh or metal lath, overlapping around the heavy expanded metal. Make sure nails or staples used for fastening mesh penetrate studs at least 1" (25mm).

4)Mortar must be "thin set" or "thin bed" type inherently polymer modified. If not modified, you should add a synthetic latex additive. Mix to a firm, moist consistency. Using a plasterer's or mason's trowel apply mortar 1/2"(13mm)to3/4"(19mm)thicktoprepared surface area. Do not spread more than a workable area so that the mortar will not set up before stone or brick is applied.

Note: Remove the fireplace doors and louvers and store them in a safe place until all the masonry work is finished. Acid from the cleaning operation will permanently damage gold plating.

5)If additional mortar is required, use a grout bag to fi ll in joints. Care must be taken to avoid smearing on the surface of stone or brick. Accidental smears should be removed only after mortar has become crumbly, using a whisk broom or dry bristle brush. Do not use a wet brush or a wire brush.

6)When mortar joints have become fi rm (thumb-print dry) they should be pointed up with a wood stick or metal jointing tool.

INSTALLATION

Discharge Vent Frame

FPI FP90 Wood Fireplace

17

Image 17
Contents FP90 Wood Fireplace Regency Fireplace Product Table of Contents Safety Label for FP90 Safety LabelProduct Details InstallationPlease Retain this Manual for Future Reference Dimensions and Specifications Clearances and Height Requirements Fireplace Enclosure Framing Installation of Nailing StripsHearth Extension Framing DetailsBefore YOU Start Installation ComponentsChimney System Considerations Chase EnclosureOn E Installation Measurements / Framing DetailsInstalling STAND-OFFS Assembly StepsInstalling the Chimney System SET the Regency FP90 Into PositionSpecial Notes Offset Chimney InstallationElevation FT # of Elbows Above SEA Level Installing Outside AIR KITInstalling Blower Systems Wiring the FP90Gravity AIR Feed KIT Option Internal Blower with Thermo-DiscCompleting The Facing Non-self Supporting, Thin Veneer Facades InstallationFinishing Regency FP90 Masonry Retainer Kit Option Completing The Mantle Finishing DetailsMasonry Liner Bricks Glass Secondary AIR Tube InstallationSafety Precautions Ash Drawer Kit InstallationASH Drawer KIT OptionDiagram FAN InstallationMasonry Cover Plate Installation Installation 60W xAREA Finishing Trim KIT InstallationStandoff Installing the Handles on the Screen Fireplace Screen InstallationInstalling the Top Louver Installing the Bottom Louver Regency Louver InstallationInstalling the Facing Guide Excalibur Faceplate InstallationExcalibur Accent KIT Installation General Heatwave KIT not EPA ApprovedListings and Code Approvals InformationMinimum Framing Clearances InstallationR90 / EX90 Models All ModelsOperation MaintenanceWiring Diagram Operating Instructions Safety GuidelinesOperating Instructions First FirePlated Finishes Glass Cleaning MaintenanceGlass Removal Replacement Door GasketParts LIST- Firebox & Body Parts ListParts LIST- BAFFLES, DOOR, Options FPI FP90 Wood Fireplace Warranty Lifetime WarrantyInstaller Please complete the following information